Task.PreleveledFinish Property (Project)

office 365 dev account|Last Updated: 6/12/2017
|
1 Contributor

Gets the finish date of a task before leveling occurred. Read-only Variant.

Syntax

expression. PreleveledFinish

expression A variable that represents a Task object.

Example

The following example calculates the difference, if any, between the projected finish date and the projected finish date before the task was leveled for each task in the project, and then displays those that changed.

Sub DateDifferences() 
 Dim T As Task, Results As String 

 For Each T In ActiveProject.Tasks 
 If Not (T Is Nothing) Then 
 ' Tasks that have never been leveled return "NA" 
 If T.PreleveledFinish <> "NA" And T.Finish <> T.PreleveledFinish Then 
 Results = Results &; T.Name &; ": " &; _ 
 DateDiff("d", T.PreleveledFinish, T.Finish) &; _ 
 " days" &; vbCrLf 
 End If 
 End If 
 Next T 

 If Results <> "" Then MsgBox Results 

End Sub