Task.OutlineLevel Property (Project)

office 365 dev account|Last Updated: 6/12/2017
|
1 Contributor

Gets the level of the task in the outline hierarchy. Read/write Integer.

Syntax

expression. OutlineLevel

expression A variable that represents a Task object.

Remarks

A task with an outline level of 1 is at the highest level in the outline; there are no summary tasks above it. A task with an outline level of 3 has two summary tasks above it.