PjConstraint Enumeration (Project)

office 365 dev account|Last Updated: 6/12/2017
|
1 Contributor

Contains constants that specify the type of constraint.

NameValueDescription
pjALAP1Task occurs as late as possible in the schedule without delaying subsequent tasks.
pjASAP0Task occurs as soon as possible in the schedule. This is the default constraint type for tasks.
pjFNET6Task finishes on or after the constraint date.
pjFNLT7Task finishes on or before the constraint date.
pjMFO3Task finishes on the constraint date.
pjMSO2Task starts on the constraint date.
pjSNET4Task starts on or after the constraint date.
pjSNLT5Task starts on or before the constraint date.