Task to complete performance index is the ratio of remaining available budget to remaining scheduled cost as of the status date.

Namespace:  WebSvcProject
Assembly:  ProjectServerWebServices (in ProjectServerWebServices.dll)

public double TASK_TCPI { get; set; }

Property Value

Type: System.Double

Read-only.

TASK_TCPI = (TB_COST - TASK_BCWP) / (TB_COST - TASK_ACWP)