ProjectDataSet.TaskRow::TASK_DUR_FMT property
The task duration format indicates the display format of the duration value, and whether the duration is considered an estimate rather than a firm value.
Namespace: WebSvcProject
Assembly: ProjectServerServices (in ProjectServerServices.dll)
Task.DurationFormat is an enumeration that contains the valid values for this field. Cast the enumerated value to an int for storage in this property. Assigning a value to this field affects
TASK_DUR_IS_EST. For example, if you assign the value of EstDay to this field, TASK_DUR_IS_EST returns true.
Note |
|---|
When creating a TaskRow object, you must specify TASK_DUR_FMT. Otherwise, later use of the project in Project Professional can result in unpredictable behavior, including possible data loss. |
int Value | enum Value | Description | Estimated |
|---|---|---|---|
3 | Minute | Minutes | No |
4 | EMinute | Elapsed minutes | No |
5 | Hour | Hours | No |
6 | EHour | Elapsed hours | No |
7 | Day | Days | No |
8 | EDay | Elapsed days | No |
9 | Week | Weeks | No |
10 | EWeek | Elapsed weeks | No |
11 | Month | Months | No |
12 | EMonth | Elapsed months | No |
19 | Percent | Percentage | No |
20 | EPercent | Elapsed percentage | No |
21 | Null | No value | No |
37 | EstHour | Estimated hours | Yes |
38 | EEstHour | Elapsed estimated hours | Yes |
39 | EstDay | Estimated days | Yes |
40 | EEstDay | Elapsed estimated days | Yes |
41 | EstWeek | Estimated weeks | Yes |
42 | EEstWeek | Elapsed estimated weeks | Yes |
43 | EstMonth | Estimated month | Yes |
44 | EEstMonth | Elapsed estimated months | Yes |
51 | EstPercent | Estimated percentage | Yes |
52 | EEstPercent | Elapsed estimated percentage | Yes |
53 | None | No display format | Yes |
Note