RES_VAC Property
TOC
Collapse the table of content
Expand the table of content
The document is archived and information here might be outdated

ProjectDataSet.ProjectResourceRow.RES_VAC Property

Office 2007

Specifies the difference between the BAC (budgeted at completion) or baseline cost and EAC (estimated at completion) cost for this resource for all assignments.

Namespace:  WebSvcProject
Assembly:  ProjectServerWebServices (in ProjectServerWebServices.dll)

public double RES_VAC { get; set; }

Property Value

Type: System.Double

Read-only. RES_VAC is calculated as shown in the following formula.

RES_VAC = RB_BASE_COST - RES_COST.

This value includes the cost of actual work plus any per-use costs for the resource to date.