ProjectDataSet.ProjectResourceRow.RES_CV property

Office 2013 and later

Specifies the difference between the resource's BCWP (budgeted cost of work performed) and ACWP (actual cost of work performed).

Namespace:  WebSvcProject
Assembly:  ProjectServerServices (in ProjectServerServices.dll)

public double RES_CV { get; set; }

Property value

Type: System.Double

Read-only. RES_CV is calculated as shown in the following formula.

RES_CV = RES_BCWP - RES_ACWP

RES_CV shows the difference between how much it was expected to cost and how much it actually cost to achieve the current level of completion up to the status date or today's date.