ProjWBSUpdateController.updateEffortAtComplete Method [AX 2012]
Updates effort at complete given new effort to complete.
public void updateEffortAtComplete(
ElementNumber _elementNumber,
Hours _newEffortToComplete,
PSAActivitySetup _psaActivitySetup)
Run On
CalledParameters
- _elementNumber
- Type: ElementNumber Extended Data Type
Element number of the task for which to update effort at complete.
- _newEffortToComplete
- Type: Hours Extended Data Type
New effort to complete.
- _psaActivitySetup
- Type: PSAActivitySetup Table
PSAAcitivitySetup record of the given task.
Community Additions
ADD
Show: