ProjectDataSet.TaskRow.TASK_TYPE Property

Office 2007

Task type can be fixed units, fixed duration, or fixed work.

Namespace:  WebSvcProject
Assembly:  ProjectServerWebServices (in ProjectServerWebServices.dll)

public int TASK_TYPE { get; set; }

Property Value

Type: System.Int32

TASK_TYPE controls the effect that editing work, assignment units, or duration has on the calculation of the other two fields. The options are:

  • 0 - Fixed Units (default) - The number of Assignment Units remains constant, regardless of the amount of work or duration on the task.

  • 1 - Fixed Duration - The duration of the task remains constant, regardless of the number of resources (Assignment Units) assigned or the amount of work

  • 2 - Fixed Work - The amount of work remains constant, regardless of any change in duration or the number of resources (Assignment Units) assigned to the task.