ProjectDataSet.TaskRow.TASK_FIXED_COST_ACCRUAL Property

Office 2007

Fixed cost accrual indicator indicates how fixed costs are to be accrued in a task.

Namespace:  WebSvcProject
Assembly:  ProjectServerWebServices (in ProjectServerWebServices.dll)

public short TASK_FIXED_COST_ACCRUAL { get; set; }

Property Value

Type: System.Int16

  • 1 = Start; costs are accrued as soon as the task starts, as indicated by a date entered in the ActualStart field.

  • 2 = End; costs are not incurred until remaining work is zero.

  • 3 = Pro-rated (default); costs accrue as work is scheduled to occur and as actual work is reported.