ProjectDataSet.ProjectRow.PROJ_OPT_SPREAD_PCT_COMP Property

Indicates whether percent complete is spread to the status date or to the task finish date.

Namespace:  [Project Web service]
Service reference: http://ServerName:32843/[Project Service Application GUID]/PSI/Project.svc
Web service reference: http://ServerName/ProjectServerName/_vti_bin/PSI/Project.asmx?wsdl

public bool PROJ_OPT_SPREAD_PCT_COMP { get; set; }

Property Value

Type: System.Boolean

true if percent complete is spread to the status date; otherwise, false. PROJ_OPT_SPREAD_PCT_COMP maps to the Edits to total task % complete will be spread to the status date option on the Calculation tab of the Options dialog box in Project Professional.

The default value for new projects is determined by the enterprise global template. If there is no enterprise global template value, the default value is false.