ProjectDataSet.ProjectRow.PROJ_OPT_CRITICAL_SLACK_LIMIT property

Specifies the number of days that a task can go past its end date before Project marks that task as critical.

Namespace:  WebSvcProject
Assembly:  ProjectServerServices (in ProjectServerServices.dll)

public int PROJ_OPT_CRITICAL_SLACK_LIMIT { get; set; }

Property value

Type: System.Int32

The default value of PROJ_OPT_CRITICAL_SLACK_LIMIT for new projects is determined by the enterprise global template. If there is no enterprise global template value, the default value is zero days, which is the default slack value in Project Professional (on the Calculation tab in the Options dialog box).