ProjectDataSet.AssignmentRow properties
The ProjectDataSet.AssignmentRow type exposes the following members.
Properties
Name | Description | |
---|---|---|
AB_COST | Specifies the total cost of the resource for work on this task, calculated at the time the baseline was saved. | |
AB_COST_PER_USE | Specifies the RES_COST_PER_USE that is incurred for this resource on this task, calculated at the time the baseline was saved. | |
AB_FINISH | Specifies the date on which this resource will complete work on this task, calculated at the time the baseline was saved. | |
AB_START | Specifies the date on which this resource starts work on this task, calculated at the time the baseline was saved. | |
AB_WORK | Specifies the amount of work this resource spends on this task, calculated at the time the baseline was saved. | |
AssignmentHyperlinkHref | Gets the assignment hyperlink. | |
ASSN_ACT_COST | Specifies the cost of work that has been performed by this resource on this task to date. | |
ASSN_ACT_FINISH | Specifies the date and time when a task or assignment was actually completed. | |
ASSN_ACT_OVT_COST | Specifies the cost incurred for overtime that has been performed on this task by this resource. | |
ASSN_ACT_OVT_WORK | Specifies the actual amount of overtime work that has been performed by this resource on this task. | |
ASSN_ACT_START | Specifies the date and time when the resource actually began work on the task. | |
ASSN_ACT_WORK | Specifies the amount of work that this resource has done on this task. | |
ASSN_ACWP | Specifies the assignment's actual cost of work performed (ACWP). | |
ASSN_BCWP | Specifies the assignment's budgeted cost of work performed (BCWP). | |
ASSN_BCWS | Specifies the cumulative baseline costs to date. | |
ASSN_BOOKING_TYPE | Specifies the default booking type for this assignment. | |
ASSN_BUDGET_COST | Specifies the budgeted cost for this resource on this task. | |
ASSN_BUDGET_WORK | Specifies the budgeted work for this resource on this task. | |
ASSN_COST | Specifies the total projected cost for this resource and this task. | |
ASSN_COST_RATE_TABLE | Specifies the resource's cost rate table to use on this task. | |
ASSN_COST_VAR | Specifies the difference between the baseline cost and the total cost for this resource on this task. | |
ASSN_CV | Specifies the difference between the budgeted cost and the actual cost to achieve the assignment completion status to date. | |
ASSN_DELAY | Specifies the amount of time that the resource is to wait after the task start date before starting work on the task. | |
ASSN_DELAY_FMT | Indicates the desired display format of ASSN_DELAY, and whether the duration is considered only an estimate rather than a firm value. | |
ASSN_DEMAND_REQ | Indicates how to assign resources when using the resource substitution wizard. | |
ASSN_ENTSUMPROJID | Specifies the ID of the project to which this summary assignment belongs. | |
ASSN_FINISH_DATE | Specifies the date and time that this resource is scheduled to finish this task. | |
ASSN_FINISH_VAR | Specifies the duration that represents the difference between the baseline finish date of a task or assignment and its current finish date. | |
ASSN_HAS_LINKED_FIELDS | Indicates whether the assignment has linked fields. | |
ASSN_HYPERLINK_ADDRESS | Specifies the URL for the hyperlink that is associated with this assignment. | |
ASSN_HYPERLINK_FRIENDLY_NAME | Specifies the display text for the hyperlink associated with this assignment. | |
ASSN_IS_CONFIRMED | Indicates whether this resource has accepted or rejected the task assignment. | |
ASSN_IS_OVERALLOCATED | Indicates whether the resource is assigned to more work on this assignment than can be done within the resource's normal working capacity. | |
ASSN_IS_PUBLISHED | Indicates whether the assignment is published; Project Server sets this property internally. | |
ASSN_LEVELING_DELAY | Specifies the amount of time that an assignment is delayed from the scheduled start date as a result of resource leveling. | |
ASSN_MATERIAL_RATE_FMT | Indicates the units in which the material rate is displayed in Project. | |
ASSN_NOTES | Specifies the notes that are entered in the Assignment Details Dialog Box. | |
ASSN_OVT_COST | Specifies the total overtime cost for this resource on this task. | |
ASSN_OVT_WORK | Specifies the overtime work for which the resource is scheduled on this task. | |
ASSN_PARENT_UID | Specifies the unique ID of the parent assignment to this assignment. | |
ASSN_PCT_WORK_COMPLETE | Specifies the current status of an assignment, expressed as the percentage of the assignment's work that is complete. | |
ASSN_REG_WORK | Specifies the amount of time scheduled for an assignment that is charged at the resource's standard rate. | |
ASSN_REM_COST | Specifies the remaining scheduled expense that will be incurred in completing the remaining scheduled work. | |
ASSN_REM_OVT_COST | Specifies the remaining scheduled overtime expense for this resource on this task. | |
ASSN_REM_OVT_WORK | Specifies the amount of remaining scheduled overtime. | |
ASSN_REM_WORK | Specifies the amount of time still required by this resource on this task. | |
ASSN_RES_TYPE | Indicates whether the resource is a material resource or a work resource. | |
ASSN_RESPONSE_PENDING | Indicates whether an acknowledgment as received from this resource regarding this task. | |
ASSN_RESUME_DATE | Specifies the date and time when a resource resumes work on this assignment. | |
ASSN_START_DATE | Indicates that the assignment start date is the date and time when this resource begins work on this task. | |
ASSN_START_VAR | Specifies the amount of time that represents the difference between the baseline start date of this assignment and its currently scheduled start date. | |
ASSN_STOP_DATE | Specifies when work on this assignment will stop, even if the assignment is not finished. | |
ASSN_SV | Specifies the difference in cost terms between the current progress and the baseline planned progress for this resource on this task. | |
ASSN_UID | Specifies the unique identifier for the assignment. | |
ASSN_UNITS | Specifies how much work the resource performs on this assignment, expressed as a percentage of the resource's theoretical full capacity. | |
ASSN_UPDATE_NEEDED | Indicates whether to send a Project Server update to the resource because of a change to the assignment. | |
ASSN_VAC | Specifies the difference between the BAC (budgeted at completion) cost or baseline cost and the EAC (estimated at completion) cost of this resource on this task. | |
ASSN_WORK | Specifies the total assignment work based on the assignment span and the assignment units for the assigned resource. | |
ASSN_WORK_CONTOUR | Indicates how to distribute work for an assignment across the duration of the assignment. | |
ASSN_WORK_VAR | Specifies the difference between baseline work and the currently scheduled work. | |
CREATED_DATE | Specifies the date and time when this row was created. | |
HasErrors | (Inherited from DataRow.) | |
Item[Int32] | (Inherited from DataRow.) | |
Item[String] | (Inherited from DataRow.) | |
Item[DataColumn] | (Inherited from DataRow.) | |
Item[Int32, DataRowVersion] | (Inherited from DataRow.) | |
Item[String, DataRowVersion] | (Inherited from DataRow.) | |
Item[DataColumn, DataRowVersion] | (Inherited from DataRow.) | |
ItemArray | (Inherited from DataRow.) | |
MOD_DATE | Specifies the date and time when this row was modified. | |
PROJ_NAME | Specifies the name of the project to which this assignment belongs. | |
PROJ_OPT_CURRENCY_DIGITS | Specifies the number of digits that appear after the decimal in currency values. | |
PROJ_OPT_CURRENCY_POSITION | Specifies the placement of the currency symbol in relation to the currency value. | |
PROJ_OPT_CURRENCY_SYMBOL | Specifies the symbol used to represent the type of currency used in the project. | |
PROJ_UID | Specifies the foreign key into the ProjectDataSet.ProjectRow object. | |
RES_BOOKING_TYPE | Indicates the default booking type for the resource on this project. | |
RES_GROUP | Specifies any code, abbreviation, or number you want to enter as part of a resource's information. | |
RES_MATERIAL_LABEL | Indicates the unit of measurement you enter for supplies or other consumable items that are used to complete tasks in a project. | |
RES_NAME | Specifies the name of the resource. | |
RES_TYPE | Specifies the resource type. | |
RES_UID | Specifies the unique ID of the resource that is associated with this assignment. | |
RES_UID_OWNER | Specifies the unique ID of the resource that is the owner of this assignment. | |
ResourceIsGeneric | Indicates whether this resource is a generic placeholder resource. | |
RowError | (Inherited from DataRow.) | |
RowState | (Inherited from DataRow.) | |
Table | (Inherited from DataRow.) | |
TASK_NAME | Specifies the name of the task that is associated with this assignment. | |
TASK_UID | Specifies the unique ID of the task that is associated with this assignment. | |
WASSN_LOCKDOWN_BY_MANAGER | Indicates that an assignment is locked and cannot be changed. |