FixedCostAccrual enumeration

Office 2013

Specifies how and when fixed costs are to be charged to the cost of a task.

Namespace:  Microsoft.ProjectServer.Client
Assembly:  Microsoft.ProjectServer.Client (in Microsoft.ProjectServer.Client.dll)

public enum FixedCostAccrual

Member nameDescription
NotSpecifiedValue=0. The fixed cost accrual mode is not specified. This constant is used in place of a DBNull value.
StartValue=1. Costs are accrued as soon as the task starts. A task begins when a date is entered in the ActualStart field.
EndValue=3. Costs are not accrued until the remaining work is zero.
ProratedValue=2. This is the default value. Costs accrue as work is scheduled to occur and as actual work is reported.

The FixedCostAccrual enumeration in the CSOM is equivalent to Task.FixedCostAccrual in the Microsoft.Office.Project.Server.Library namespace. The FixedCostAccrual constants can be used with the following properties:

Show: