PS.AccrueAt enumeration (ps.js)
Specifies the cost accrual mode, which defines how and when resource costs are charged to the cost of a task.
Last modified: February 13, 2013
Applies to: Project Professional 2013 | Project Server 2013
PS.AccrueAt
The AccrueAt enumeration has the following members.
|
Member |
Value |
Description |
|---|---|---|
|
notSpecified |
0 |
The cost accrual mode is not specified. This constant is used in place of a DBNull value. |
|
start |
1 |
Costs are accrued as soon as the task assignment starts. A task assignment begins when a date is entered in the ActualStart field. |
|
end |
2 |
Costs are not accrued until the remaining work is zero. |
|
prorated |
3 |
Costs accrue as work is scheduled to occur and as actual work is reported. This is the default value. |