PS.FixedCostAccrual enumeration (ps.js)
Specifies how and when fixed costs are to be charged to the cost of a task.
Last modified: February 12, 2013
Applies to: Project Professional 2013 | Project Server 2013
PS.FixedCostAccrual
The FixedCostAccrual enumeration has the following members.
|
Member |
Value |
Description |
|---|---|---|
|
notSpecified |
0 |
The fixed cost accrual mode is not specified. This constant is used in place of a DBNull value. |
|
start |
1 |
Costs are accrued as soon as the task starts. A task begins when a date is entered in the ActualStart field. |
|
prorated |
2 |
This is the default value. Costs accrue as work is scheduled to occur and as actual work is reported. |
|
end |
3 |
Costs are not accrued until the remaining work is zero. |