TrackingMode enumeration
Collapse the table of content
Expand the table of content

TrackingMode enumeration

Office 2013

Specifies the modes for tracking task progress.

Namespace:  Microsoft.ProjectServer.Client
Assembly:  Microsoft.ProjectServer.Client (in Microsoft.ProjectServer.Client.dll)

'Declaration
Public Enumeration TrackingMode
'Usage
Dim instance As TrackingMode

Member nameDescription
NoneValue=0. Use free-form tracking for tasks, where resources can report hours by using any method (actual hours, percent complete, or timephased).
TimePhasedValue=1. Use timephased tracking for tasks, by hours of work done per period.
PercentCompleteValue=2. Track tasks by percentage of work complete.
ActualHoursValue=3. Track tasks by actual hours of work done and work remaining.

You can set the tracking mode in the Tracking Method section of the Task Settings and Display page in Project Web App (http://ServerName/ProjectServerName/_layouts/15/pwa/Admin/Statusing.aspx).