Task.FixedCostAccrual enumeration
Office 2013 and later
Specifies how and when fixed costs are to be charged to the cost of a task.
Namespace: Microsoft.Office.Project.Server.Library
Assembly: Microsoft.Office.Project.Server.Library (in Microsoft.Office.Project.Server.Library.dll)
| Member name | Description | |
|---|---|---|
| Start | Value=1. Costs are accrued as soon as the task starts. A task begins when a date is entered in the ActualStart field. | |
| End | Value=3. Costs are not accrued until the remaining work is zero. | |
| Prorated | Value=2. Costs accrue as work is scheduled to occur and as actual work is reported. This is the default value. |