Summary Element

Office 2007

This content is outdated and is no longer being maintained. It is provided as a courtesy for individuals who are still using these technologies. This page may contain URLs that were valid when originally published, but now link to sites or pages that no longer exist.

Indicates whether the task is a summary task or the assignment is on a summary task.


<Summary>
  BooleanValue
</Summary>

Minimum: 0

Maximum: 1

A text value of type boolean is required.

Value

Description

0

False

1

True

NoteNote

You should generally assign resources to individual subtasks, not to a summary task. For more information, see Assign a resource to a task in the Project 2007 Help and How-to guide.