OvertimeWork Element (SetAssignmentWorkData)

This content is outdated and is no longer being maintained. It is provided as a courtesy for individuals who are still using these technologies. This page may contain URLs that were valid when originally published, but now link to sites or pages that no longer exist.

The OvertimeWork element is introduced in Microsoft Office Project 2007 only for forward-compatibility.

<OvertimeWork>
</OvertimeWork>

Attributes

Attribute

Description

None

Child Elements

None

Parent Elements

PeriodChange

Occurrences

Minimum: 0

Maximum: Unbounded

Text Value

Timephased updates to the Actual Overtime Work field are not supported in Project 2007. You can perform a simple update to the Actual Overtime Work field by using the UpdateStatus method.

For more information, see the ChangeList Schema Reference.