Project estimates report (ProjEstimateList) [AX 2012]
Updated: October 11, 2011
Applies To: Microsoft Dynamics AX 2012 R3, Microsoft Dynamics AX 2012 R2, Microsoft Dynamics AX 2012 Feature Pack, Microsoft Dynamics AX 2012
Use this report to view and print estimates by estimate date and period code. You can select to include the status of the project estimates and any warnings for an estimate on the report.
When you generate this report, the following default parameters are displayed. You can use these parameters to filter the data that will be displayed on the report. For more information, see Filter the data on a report.
| Field | Description | ||
|---|---|---|---|
| Period code | Select the period code. The period code that you select determines the start dates that you select in the Estimate date field. | ||
| Estimate date | Select a date for the estimate projects that you want to include on the report.
| ||
| Included warnings | Select whether to include warning types on the report from the following options:
| ||
| Included estimate status | Select the estimate statuses to include on the report. |
The following table explains where to find the report in the Application Object Tree (AOT) and how to navigate to the report in the Microsoft Dynamics AX client.
| Detail | Description |
|---|---|
| Name of report in the AOT | ProjEstimateList |
| Location of report in the AOT | SSRS Reports\Reports\ProjEstimateList |
| Menu item of the report | ProjEstimateList |
| Navigation to the report | Click Project management and accounting > Reports > Estimates > Project estimates. |
The data on this report comes from the following sources:
-
ProjEstimateListDP.processReport
-
ProjEstimateListTmp table
Note |
|---|
| To determine where the data in the temp tables comes from, view the cross-references for the ProjEstimateListDP.processReport class. |
If you are a developer, you can learn more about where the data on a report comes from by using the following procedure.
-
Open the AOT.
-
Locate the report in the SSRS Reports\Reports node.
-
Right-click the report and click Add-Ins > Cross-reference > Using (instant view).
Announcements: To see known issues and recent fixes, use Issue search in Microsoft Dynamics Lifecycle Services (LCS).
Note