<Resource> Element

A resource in the project. There must be at least one resource in each Resources collection.

Element Properties

Property Value
Data Type ComplexType
Minimum Occurrences 0
Maximum Occurrences Unbounded
Default Value N/A
Abstract False
Nillable False
Element Constraints Sequence

Parent Elements

Resources

Child Elements

List of Child Elements

Element Required/Optional Description
<UID> Required The unique ID for the resource.
<ID> Optional The position identifier of the resource within the list of resources.
<Name> Optional The name of the resource; must be unique within the enterprise, whether or not the resource is active.
<Type> Optional The resource type (work or material).
<IsNull> Optional Indicates whether the resource is a null resource.
<Initials> Optional The initials of a resource name.
<Phonetics> Optional Contains phonetic information in either Hiragana or Katakana for resource names; used only in the Japanese version of Microsoft Office Project 2003.
<NTAccount> Optional The Microsoft Windows NT Account name for a resource.
<MaterialLabel> Optional The unit of measurement entered for a material resource, for example, tons, boxes, or cubic yards.
<Code> Optional A code, abbreviation, or number entered as part of a resource's information.
<Group> Optional The name of the group the resource belongs to.
<WorkGroup> Optional The messaging method used to communicate with a project team.
<EmailAddress> Optional The e-mail address of a resource.
<Hyperlink> Optional The title or explanatory text for a hyperlink associated with a resource.
<HyperlinkAddress> Optional The address for a hyperlink associated with a resource.
<HyperlinkSubAddress> Optional The specific location in a document within a hyperlink associated with a resource.
<MaxUnits> Optional The maximum percentage, or number of units, that represents the maximum amount that a resource is available to accomplish any tasks during the current time period.
<PeakUnits> Optional The maximum percentage, or number of units, that a resource is assigned at any one time for all tasks assigned to that resource.
<OverAllocated> Optional Indicates whether a resource is assigned to do more work on all assigned tasks than can be done within the resource's normal work capacity.
<AvailableFrom> Optional The starting date that a resource is available for work at the units specified for the current time period.
<AvailableTo> Optional The ending date that a resource will be available for work at the units specified for the current time period.
<Start> Optional The date and time that a resource is scheduled to start work on all assigned tasks.
<Finish> Optional The date and time that a resource is scheduled to complete work on all assigned tasks.
<CanLevel> Optional Indicates whether resource leveling can be performed with a resource.
<AccrueAt> Optional Indicates how and when resource standard and overtime costs are to be charged, or accrued, to the cost of a task.
<Work> Optional The total amount of work scheduled to be performed by a resource on all assigned tasks.
<RegularWork> Optional The total amount of non-overtime work scheduled to be performed for all assignments assigned to a resource.
<OvertimeWork> Optional The amount of overtime to be performed for all tasks assigned to a resource and charged at the resource's overtime rate.
<ActualWork> Optional The actual amount of work that has already been done for all assignments assigned to a resource.
<RemainingWork> Optional The amount of time, or person-hours, still required by a resource to complete all assigned tasks.
<ActualOvertimeWork> Optional The actual amount of overtime work already performed for all assignments assigned to a resource.
<RemainingOvertimeWork> Optional The remaining amount of overtime required by a resource to complete all tasks.
<PercentWorkComplete> Optional The current status of all tasks assigned to a resource, expressed as the total percentage of the resource's work that has been completed.
<StandardRate> Optional The rate of pay for regular, non-overtime work performed by a resource.
<StandardRateFormat> Optional The units used to display the standard rate.
<Cost> Optional The total scheduled cost for a resource for all assigned tasks, based on costs already incurred for work performed by the resource on all assigned tasks in addition to the costs planned for all remaining work.
<OvertimeRate> Optional The rate of pay for overtime work performed by a resource.
<OvertimeRateFormat> Optional The units used to display the overtime rate.
<OvertimeCost> Optional The total overtime cost for a resource on all assigned tasks.
<CostPerUse> Optional The cost that accrues each time a resource is used.
<ActualCost> Optional The sum of costs incurred for the work already performed by a resource for all assigned tasks.
<ActualOvertimeCost> Optional The cost incurred for overtime work already performed by a resource for all assigned tasks.
<RemainingCost> Optional The remaining scheduled expense that will be incurred in completing the remaining work assigned to a resource.
<RemainingOvertimeCost> Optional The remaining scheduled overtime expense of a resource that will be incurred in completing the remaining planned overtime work by a resource on all assigned tasks.
<WorkVariance> Optional The difference between a resource's total baseline work and the currently scheduled work.
<CostVariance> Optional The difference between the baseline cost and total cost for a resource.
<SV> Optional The difference in cost between the current progress and the baseline plan of all the resource's assigned tasks up to the status date or today's date; also called earned value schedule variance.
<CV> Optional The difference between how much it should have cost for the resource to achieve the current level of completion, and how much it has actually cost to achieve the current level of completion, up to the status date or today's date.
<ACWP> Optional The sum of actual cost of work performed (ACWP) values for all of a resource's assignments, up to the status date or today's date.
<CalendarUID> Optional The unique ID for the calendar associated with this resource.
<Notes> Optional Notes about a resource.
<BCWS> Optional The rolled-up summary of a resource's BCWS values for all assigned tasks; also called budgeted cost of work scheduled.
<BCWP> Optional The rolled-up summary of a resource's BCWP values for all assigned tasks, calculated up to the status date or today's date; also called budgeted cost of work performed.
<IsGeneric> Optional Indicates whether the resource is an enterprise-level generic resource.
<IsInactive> Optional Indicates whether the resource is an active (enabled) or inactive user.
<IsEnterprise> Optional Specifies whether the resource is an enterprise resource.
<BookingType> Optional Specifies the booking type of the resource (committed or proposed).
<ActualWorkProtected> Optional Specifies the duration through which actual work is protected.
<ActualOvertimeWorkProtected> Optional Specifies the duration through which actual overtime work is protected.
<ActiveDirectoryGUID> Optional The Active Directory GUID for the resource.
<CreationDate> Optional The date that the project, resource, or assignment was created.
<ExtendedAttribute> Optional A custom field definition associated with a resource.
<Baseline> Optional A set of project estimates used for tracking purposes.
<OutlineCode> Optional A custom tag defined for a resource that enables an alternate project structure.
<AvailabilityPeriods> Optional The collection of dates the resource is available.
<Rates> Optional The collection of pay rates for the resource.
<TimephasedData> Optional The timephased data block associated with the resource.