ProjectDataSet.ProjectRow.PROJ_OPT_MOVE_ACTUAL_IF_LATER Property

Office 2007

Indicates whether to move the end date of completed parts forward to the status date, if the actual end date falls before the status date.

Namespace:  WebSvcProject
Assembly:  ProjectServerWebServices (in ProjectServerWebServices.dll)
public bool PROJ_OPT_MOVE_ACTUAL_IF_LATER { get; set; }

Property Value

Type: System.Boolean
true if Project Server moves the end date of completed parts forward to the status date.

PROJ_OPT_MOVE_ACTUAL_IF_LATER maps to the And move end of completed parts forward to status date option in the Calculation tab of the Options dialog box in Microsoft Office Project Professional.

The default value for new projects is determined by the enterprise global template. If there is no enterprise global template value, the default value is false.