Information
The topic you requested is included in another documentation set. For convenience, it's displayed below. Choose Switch to see the topic in its original location.

ProjectDataSet.ProjectRow.PROJ_OPT_MOVE_ACTUAL_TO_STATUS Property

Office 2007

Indicates whether to move the end date of completed parts back to the status date, if the actual end data falls after the status date.

Namespace:  WebSvcProject
Assembly:  ProjectServerWebServices (in ProjectServerWebServices.dll)

public bool PROJ_OPT_MOVE_ACTUAL_TO_STATUS { get; set; }

Property Value

Type: System.Boolean
true if Project Server moves the end date of completed parts back to the status date.

PROJ_OPT_MOVE_ACTUAL_TO_STATUS maps to the Move end of completed parts after status date back to status date option in the Calculation tab of the Options dialog box in Microsoft Office Project Professional.

The default value for new projects is determined by the enterprise global template. If there is no enterprise global template value, the default value is false.