Day Object (Project)

Represents a day in a month. The Day object is a member of the Days collection.

Using the Day Object

Use Days ( Index ), where Index is the day index number or PjWeekday constant, to return a single Day object. The following example counts the number of working days in the month of September 2008 for each selected resource.

Dim R As Resource, D As Integer, WorkingDays As Integer 
 
For Each R In ActiveSelection.Resources() 
    WorkingDays = 0 
    With R.Calendar.Years(2008).Months(pjSeptember) 
        For D = 1 To .Days.Count 
            If .Days(D).Working = True Then 
                WorkingDays = WorkingDays + 1 
            End If 
        Next D 
    End With 
    MsgBox "There are " & WorkingDays & " working days in " _ 
        & R.Name & "'s calendar." 
Next R

Using the Days Collection

Use the Days property to return a Days collection. The following example counts the number of working days in the month of September 2008.

ActiveProject.Calendar.Years(2008).Months(pjSeptember).Days.Count