ValidationConst.s_max_day Field

Value = 24107. The maximum number of days after the Julian date of the minimum project date.

Namespace:  Microsoft.Office.Project.Server.Library
Assembly:  Microsoft.Office.Project.Server.Library (in Microsoft.Office.Project.Server.Library.dll)

Syntax

'Declaration
Public Const s_max_day As Integer
'Usage
Dim value As Integer

value = ValidationConst.s_max_day
public const int s_max_day

Remarks

Microsoft Project Server 2010 cannot calculate days after December 31, 2049 or before January 1, 1984. The s_max_day value = (Julian date of the maximum project date) – (Julian date of the minimum project date). That is, 2469808 – 2445701 = 24107.

The Julian date is the number of days since January 1, 4713 BC.