Allocate 110%–125% of the Hardware Resources to the Hyper-V Virtual Machines
Plan to allocate 110% to 125% of the hardware resources required by a physical hardware solution to the Hyper-V virtual machines used for the solution. By configuring the Hyper-V virtual machine with additional resources, you will ensure that it can provide performance on par with physical hardware while accommodating any overhead required by Hyper-V virtualization technology. Follow the guidance in the “Planning the Environment for BizTalk Server” section of the BizTalk Server Operations Guide at http://go.microsoft.com/fwlink/?LinkId=122399 to scope the hardware requirements for the solution including:
After scoping the hardware requirements of your BizTalk Server solution, plan to configure the Hyper-V machines with 110% – 125% of the CPU, memory, and disk resources required by the physical hardware, if possible. For example, the hardware requirements of a physical BizTalk Server used by the solution is determined to be 2GB RAM, a dual core CPU running at 2GHZ, and 2x 500 GB physical disks, then ideally, the Hyper-V virtual machine used by the solution would be configured with 2.5 GB RAM, 2 or more virtual processors running >= 2.2 GHZ, and faster physical disks (typically by adding spindles or using faster disks).