Performance Testing Guidance for Web Applications
J.D. Meier, Carlos Farre, Prashant Bansode, Scott Barber, and Dennis Rea
Microsoft Corporation
September 2007
Objectives
- Learn an approach to agile performance test management.
- Learn how to maximize flexibility without sacrificing
control.
- Learn how to provide managers and stakeholders with
progress and value indicators.
- Learn how to provide a structure for capturing information
that will not noticeably impact the release schedule.
- Learn how to apply an approach designed to embrace change,
not simply tolerate it.
Overview
This chapter describes an agile approach to managing
application performance testing. As the term implies, the key to an agile approach
is flexibility. Flexibility, however, does not mean sloppiness or inefficiency.
To remain efficient and thorough in an agile environment, you may need to
change the way you are used to managing your performance testing.
Implementing an agile philosophy means different things to
different teams, ranging from perfectly implemented eXtreme Programming (XP) to
projects with many short iterations and documentation designed for efficiency.
The approach outlined in this chapter has been successfully applied by teams
across this spectrum with minimal modification.
This chapter assumes that the performance specialist is new
to the team in question and focuses on the tasks that the performance
specialist frequently drives or champions. This is neither an attempt to
minimize the concept of team responsibility nor an attempt to segregate roles.
The team is best served if the performance specialist is an integral team member
who participates in team practices, such as pairing. Any sense of segregation
is unintentional and a result of trying to simplify explanations.
This approach to managing performance testing may seem complicated
at first because it:
- Embraces change during a project’s life cycle.
- Iterates (not always in a predictable pattern).
- Encourages planning just far enough in advance for team
coordination but not so far that the plan is likely to need significant
revision in order to execute.
However, when viewed at the task or work item level, this
approach is actually an intuitive process based on the principle of continually
asking and answering the question, “What task can I do right now that will add
the most value to the project?”
How to Use This Chapter
Use this chapter to understand the approach to performance
testing in agile development environments and its relationship with the core
activities of performance testing. Also use the chapter to understand what is
accomplished during these activities. To get the most from
this chapter:
- Use the “Agile Performance Testing Activities”
section to get an overview of the approach to performance testing
in agile environments, and as quick reference guide for you and your team.
- Use the various activity sections to understand the
details of the most critical performance-testing tasks.
- Additionally, use Chapter 4 – Core Activities in this
guide to understand the common core activities involved in successful
performance testing projects. This will help you to apply the concepts underlying
those activities to a particular approach to performance testing.
Introduction to the Approach
When viewed from a linear perspective, the approach starts
by examining the software development project as a whole, the reasons why
stakeholders have chosen to include performance testing in the project, and the
value that performance testing is expected to add to the project. The results
of this examination include the team’s view of the success criteria for the
performance testing effort.
Once the success criteria are understood at a high level, an
overall strategy is envisioned to guide the general approach to achieving those
criteria by summarizing what performance testing activities are anticipated to
add the most value at various points during the development life cycle. Those
points may include key project deliveries, checkpoints, sprints, iterations, or
weekly builds. For the purposes of this chapter, these events are collectively
referred to as “performance builds”. Frequently, while the strategy is
evolving, the performance specialist and/or the team will begin setting up a
performance-test environment and a load-generation environment.
With a strategy in mind and the necessary environments in
place, the test team draws up plans for major tests or tasks identified for
imminent performance builds. When a performance build is delivered, the plan’s
tasks should be executed in priority sequence (based on all currently available
information), appropriately reporting, recording, revising, reprioritizing,
adding, and removing tasks and improving the application and the overall plan
as the work progresses.
Agile Performance-Testing Activities
This approach can be represented by using the following nine
activities:
.gif)
Figure 6.1 Agile Performance Testing
Activities
- Activity 1. Understand the Project Vision and Context.
The project vision and context are the foundation for determining what
performance-testing activities are necessary and valuable.
- Activity 2. Identify Reasons for Testing Performance.
These are not always clear from the vision and context. Explicitly
identifying the reasons for performance testing is critical to being able
to determine what performance testing activities will add the most value
to the project.
- Activity 3. Identify the Value Performance Testing Adds
to the Project. With the information gained from steps 1 and 2,
clarify the value added through performance testing and convert that value
into a conceptual performance-testing strategy.
- Activity 4. Configure the Test Environment. With a
conceptual strategy in place, prepare the necessary tools and resources to
execute the strategy as features and components become available for test.
- Activity 5. Identify and Coordinate Immediately
Valuable Tactical Tasks. Performance-testing tasks do not happen in
isolation. For this reason, the performance specialist needs to work with
the team to prioritize and coordinate support, resources, and schedules in
order to make the tasks efficient and successful.
- Activity 6. Execute Task(s). Conduct tasks in one-
to two-day segments. See them through to completion, but be willing to
take important detours along the way if an opportunity to add additional
value presents itself.
- Activity 7. Analyze Results and Report. To keep up
with an iterative process, results need to be analyzed and shared quickly.
If the analysis is inconclusive, retest at the earliest possible
opportunity. This gives the team the most time to react to performance
issues.
- Activity 8. Revisit Activities 1-3 and Consider Performance
Acceptance Criteria. Between iterations, ensure that the foundational
information has not changed. Integrate new information such as customer
feedback and update the strategy as necessary
- Activity 9. Reprioritize Tasks. Based on the test
results, new information, and the availability of features and components,
reprioritize, add to, or delete tasks from the strategy, then return to
activity 5.
Relationship to Core Performance-Testing Activities
The following graphic shows how the seven core activities described
in Chapter 4 map to the nine agile performance-testing activities.
.gif)
Figure 6.2 Relationship to Core Performance
Testing Activities
Activity 1. Understand the Project Vision and Context
The project vision and context are the foundation for
determining what performance testing is necessary and valuable. The test team’s
initial understanding of the system under test, the project environment, the
motivation behind the project, and the performance build schedule can often be
completed during a work session involving the performance specialist, the lead
developer, and the project manager (if you also have a tentative project
schedule). Decisions made during the work session can be refactored during
other iteration and work sessions as the system becomes more familiar.
Project Vision
Before initiating performance testing, ensure that you
understand the current project vision. Because the features, implementation,
architecture, timeline, and environments are likely to change over time, you
should revisit the vision regularly, as it has the potential to change as well.
Although every team member should be thinking about performance, it is the
performance specialist’s responsibility to be proactive in understanding and
keeping up to date with the relevant details across the entire team. The
following are examples of high-level project visions:
- Evaluate a new architecture for an existing system.
- Develop a new custom system to solve a specific business
problem.
- Evaluate the new software-development tools.
- As a team, become proficient in a new language or
technology.
- Re-engineer an inadequate application before a period of
peak user activity to avoid user dissatisfaction due to application
failure.
Project Context
The project context is nothing more than those factors that
are, or may become, relevant to achieving the project vision. Some examples of
items that may be relevant to your project context include:
- Client expectations
- Budget
- Timeline
- Staffing
- Project environment
- Management approach
These items will often be discussed during a project kickoff
meeting but, again, should be revisited regularly throughout the project as
more details become available and as the team learns more about the system they
are developing.
Understand the System
Understanding the system you are testing involves becoming
familiar with the system’s intent, what is currently known or assumed about its
hardware and software architecture, and the available information about the completed
system’s customer or user.
With many agile projects, the system’s architecture and
functionality change over the course of the project. Expect this. In fact, the
performance testing you do is frequently the driver behind at least some of
those changes. Keeping this in mind will help you ensure that performance-testing
tasks are neither over-planned nor under-planned before testing begins.
Understand the Project Environment
In terms of the project environment, it is most important to
understand the team’s organization, operation, and communications techniques.
Agile teams tend not to use long-lasting documents and briefings as their
management and communications methods; instead, they opt for daily stand-ups,
story cards, and interactive discussions. Failing to understand these methods at
the beginning of a project can put performance testing behind before it even
begins. Asking the following or similar questions may be helpful:
- Does the team have any scheduled meetings, stand-ups, or
scrums?
- How are issues raised or results reported?
- If I need to collaborate with someone, should I send an e-mail
message? Schedule a meeting? Use Instant Messenger? Walk over to his or
her office?
- Does this team employ a “do not disturb” protocol when an
individual or sub-team desires “quiet time” to complete a particularly
challenging task?
- Who is authorized to update the project plan or project
board?
- How are tasks assigned and tracked? Software system? Story
cards? Sign-ups?
- How do I determine which builds I should focus on for
performance testing? Daily builds? Friday builds? Builds with a special
tag?
- How do performance testing builds get promoted to the
performance test environment?
- Will the developers be writing performance unit tests? Can
I pair with them periodically so that we can share information?
- How do you envision coordination of performance-testing
tasks?
Understand the Performance Build Schedule
At this stage, the project schedule makes its entrance, and
it does not matter whether the project schedule takes the form of a desktop
calendar, story cards, whiteboards, a document, someone’s memory, or a
software-based project management system. However, someone or something must
communicate the anticipated sequence of deliveries, features, and/or hardware
implementations that relate to the performance success criteria.
Because you are not creating a performance test plan at this
time, remember that it is not important to concern yourself with dates or
resources. Instead, attend to the anticipated sequencing of performance builds,
a rough estimate of their contents, and an estimate of how much time to expect
between performance builds. The specific performance builds that will most
likely interest you relate to hardware components, supporting software, and
application functionality becoming available for investigation.
Typically, you will find during this step that you add
performance build–specific items to your success criteria, and that you start
aligning tasks related to achieving success criteria with anticipated
performance builds.
Activity 2. Identify Reasons for Testing Performance
The underlying reasons for testing performance on a
particular project are not always obvious based on just the vision and context.
Explicitly identifying the reasons for performance testing is critical to being
able to determine what performance-testing activities will add the most value
to the project.
The reasons for conducting performance testing often go
beyond a list of performance acceptance criteria. Every project has different
reasons for deciding to include, or not include, performance testing as part of
its process. Not identifying and understanding these reasons is one way to
virtually guarantee that the performance-testing aspect of the project will not
be as successful as it could have been. Examples of possible reasons to make integrated
performance testing a part of the project include the following:
- Improve performance unit testing by pairing performance
testers with developers.
- Assess and configure new hardware by pairing performance
testers with administrators.
- Evaluate algorithm efficiency.
- Monitor resource usage trends.
- Measure response times.
- Collect data for scalability and capacity planning.
It is generally useful to identify the reasons for
conducting performance testing very early in the project. Because these reasons
are bound to change and/or shift priority as the project progresses, you should
revisit them regularly as you and your team learn more about the application,
its performance, and the customer or user.
Success Criteria
It is also useful to start identifying the desired success
criteria associated with the reasons for conducting performance testing, early in
the project. As with the reasons for testing, the success criteria are bound to
change, so you should revisit them regularly as you and your team learn more
about the application, its performance, and the customer or user. Success
criteria not only include the performance requirements, goals, and targets for
the application, but also the objectives behind conducting performance testing
in the first place, including those objectives that are financial or
educational in nature. For example, success criteria may include:
- Validate that the application be able to handle X
users per hour.
- Validate that the users will experience response times of Y
seconds or less 95 percent of the time.
- Validate that performance tests predict production
performance within a +/- 10-percent range of variance.
- Investigate hardware and software as it becomes available,
to detect significant performance issues early.
- The performance team, developers, and administrators work
together with minimal supervision to tune and determine the capacity of
the architecture.
- Conduct performance testing within the existing project duration
and budget.
- Determine the most likely failure modes for the
application under higher-than-expected load conditions.
- Determine appropriate system configuration settings for
desired performance characteristics.
It is important to record the performance success criteria
in a manner appropriate to your project’s standards and expectations, in a
location where they are readily accessible to the entire team. Whether the
criteria appear in the form of a document, on story cards, on a team wiki, in a
task-management system, or on a whiteboard is important only to the degree that
it works for your team.
The initial determination of performance-testing success
criteria can often be accomplished in a single work session involving the
performance specialist, the lead developer, and the project manager. Because you
are articulating and recording success criteria for the performance-testing
effort, and not creating a performance-test plan, it is not important to
concern yourself with dates and resources.
In general, consider the following information when
determining performance-testing success criteria:
- Application performance requirements and goals
- Performance-related targets and thresholds
- Exit criteria (how to know when you are done)
- Key areas of investigation
- Key data to be collected
Activity 3. Identify the Value Performance Testing Adds to the Project
Using the information gained in activities 1 and 2, clarify
the value added through performance testing and convert that value into a
conceptual performance-testing strategy.
Now that you have an up-to-date understanding of the system,
the project, and the performance testing success criteria, you can begin conceptualizing
an overall strategy for performance-testing imminent performance builds. It is
important to communicate the strategy to the entire team, using a method that
encourages feedback and discussion.
Strategies should not contain excessive detail or narrative
text. These strategies are intended to help focus decisions, be readily
available to the entire team, include a method for anyone to make notes or
comments, and be easy to modify as the project progresses.
While there is a wide range of information that could be
included in the strategy, the critical components are the desired outcomes of
the performance testing of the performance build and anticipated tasks that
achieve that outcome. Although it seldom occurs, if you need significant
resource coordination to accomplish a task, it might make sense to complete
strategies a few performance builds in advance. Strategies are most often completed
roughly concurrent with the release of a performance build.
Discussion Points
In general, the types of information that may be valuable to
discuss with the team when preparing a performance-testing strategy for a
performance build include:
- The reason for performance testing this delivery
- Prerequisites for strategy execution
- Tools and scripts required
- External resources required
- Risks to accomplishing the strategy
- Data of special interest
- Areas of concern
- Pass/fail criteria
- Completion criteria
- Planned variants on tests
- Load range
- Tasks to accomplish the strategy
Activity 4. Configure the Test Environment
With a conceptual strategy in place, prepare the necessary tools
and resources to execute the strategy as features and components become
available for test.
Load-generation and application-monitoring tools are almost
never as easy to implement as one expects. Whether issues arise from setting up
isolated network environments, procuring hardware, coordinating a dedicated
bank of IP addresses for IP spoofing, or version compatibility between
monitoring software and server operating systems, issues always seem to arise.
Also, it is inevitable that load-generation tools always lag
behind evolving technologies and practices. Tool creators can only build in support
for the most prominent technologies, and even then, the technologies have to
become prominent before the support can be built.
This often means that the biggest challenge involved in a
performance-testing project is getting your first relatively realistic test
implemented with users generally being simulated in such a way that the
application under test cannot legitimately tell the difference between simulated
and real users. Plan for this and do not be surprised when it takes
significantly longer than expected to get it all working smoothly.
Additionally, plan to periodically reconfigure, update, add to,
or otherwise enhance your load-generation environment and associated tools
throughout the project. Even if the application under test stays the same and
the load-generation tool is working properly, it is likely that the metrics you
want to collect will change. This frequently implies some degree of change to
or addition of monitoring tools.
Activity 5. Identify and Coordinate Tasks
Performance-testing tasks do not happen in isolation. The
performance specialist needs to work with the team to prioritize and coordinate
support, resources, and schedules to make the tasks efficient and successful.
As a delivery approaches, you will want to create performance
test execution plans for each one to two days’ worth of performance-testing
tasks. This means you are likely to have several performance test execution
plans per performance build. Each of these execution plans should communicate
the remaining details needed to complete or repeat a work item or group of work
items.
Performance test execution plans should be communicated to
the team and stakeholders by using the same method(s) the strategy uses.
Depending on the pace and schedule of your project, there may be one execution
plan per strategy, or several. It is important to limit the execution plans to
one or two days of anticipated tasks for several reasons, including the
following:
- Even though each task or group of tasks is planned to take
one or two days, it is not uncommon for the actual execution to stretch to
three or even four days on occasion. If your plans are for tasks longer
than about two days and you get delayed, you are likely to have the next
performance build before completing any valuable testing on the previous
build.
- Especially on agile projects, timely feedback about
performance is critical. Even with two-day tasks and a one-week
performance build cycle, you could end up with approximately eight days
between detecting an issue and getting a performance build that addresses
that issue. With longer tasks and/or a longer period between performance
builds, those 8 days can quickly become 16.
Performance test execution plans should be communicated far
enough in advance to be shared with the team — for recommendations or
improvements, and for necessary resource coordination to take place — but
nothing further. Due to the specificity of the execution plan, preparing them
well in advance almost always leads to significant rework. In most cases, the
team as a whole will prioritize the sequence of execution of tasks.
Discussion Points
In general, the types of information that a team finds
valuable when discussing a performance test execution plan for a work item or
group of work items include:
- Work item execution method
- Specifically what data will be collected
- Specifically how that data will be collected
- Who will assist, how, and when
- Sequence of work items by priority
Activity 6. Execute Task(s)
Conduct tasks in one-to-two day segments. See them through
to completion, but be willing to take important detours along the way if an
opportunity to add additional value presents itself.
When each performance build is delivered, the performance
testing begins with the highest-priority task related to that build. Early in
the development life cycle, those tasks are likely to contain work items such
as “collaborate with administrators to tune application servers,” while later
in the development cycle, a work item might be “validate that the application
is achieving response time goals at 50 percent of peak load.”
The most important part of task execution is to remember to
modify the task and subsequent strategies as results analysis leads to new
priorities. After a task is executed, share your findings with the team, and then
reprioritize the remaining tasks, add new tasks, and/or remove planned tasks
from execution plans and strategies based on the new questions and concerns
raised by the team. When reprioritizing is complete, move on to the next-highest-priority
task.
Keys to Conducting a Performance-Testing Task
In general, the keys to conducting a performance-testing
task include:
- Analyze results immediately and revise the plan
accordingly.
- Work closely with the team or sub-team that is most relevant
to the task.
- Communicate frequently and openly across the team.
- Record results and significant findings.
- Record other data needed to repeat the test later.
- Revisit performance-testing priorities after no more than
two days.
Activity 7. Analyze Results and Report
To keep up with an iterative process, results need to be
analyzed and shared quickly. If the analysis is inconclusive, retest at the
earliest possible opportunity. This gives the team the most time to react to
performance issues.
Even though you are sharing data and preliminary results at
the completion of each task, it is important to pause periodically to
consolidate results, conduct trend analysis, create stakeholder reports, and pair
with developers, architects, and administrators to analyze results.
Periodically may mean a half-day per week, one day between performance builds,
or some other interval that fits smoothly into your project workflow.
These short pauses are often where the “big breaks” occur. Although
continual reporting keeps the team informed, these reports are generally summaries
delivered as an e-mailed paragraph with a spreadsheet attached, or a link to
the most interesting graph on the project Web site.
On their own, these reports rarely tell the whole story. One
of the jobs of the performance specialist is to find trends and patterns in the
data, which takes time. This task also tends to lead to the desire to
re-execute one or more tests to determine if a pattern really exists, or if a
particular test was flawed in some way. Teams are often tempted to skip this
step, but do not yield to that temptation. You might end up with more data more
quickly, but if you do not stop to look at the data collectively on a regular
basis, you are unlikely to extract all of the useful findings from that data
until it is too late.
Activity 8. Revisit Activities 1-3 and Consider Performance Acceptance
Criteria
Between iterations, ensure that the foundational information
has not changed. Integrate new information such as customer feedback and update
the strategy as necessary.
After the success criteria, strategies, and/or tasks have
been updated and prioritized, it is time to resume the performance-testing
process where you left off. However, this is easier said than done. Sometimes,
no matter how hard you try to avoid it, there are simply no valuable performance-testing
tasks to conduct at this point. This could be due to environment upgrades, mass
re-architecting/refactoring, significant detected performance issues that
someone else needs time to fix, and so on.
On the positive side, the performance specialist has
possibly the broadest set of skills on the entire team. This means that when
the situation arises, continued performance testing or paired performance
investigation with developers or administrators is not going to add value at
this time, and the performance specialist can be temporarily given another task
such as automating smoke tests, optimizing HTML for better performance, pairing
with a developer to assist with developing more comprehensive unit tests, and
so on. The key is to never forget that the performance specialist’s first
priority is performance testing, while these other tasks are additional
responsibilities.
Activity 9. Reprioritize Tasks
Based on the test results, new information, and the
availability of features and components, reprioritize, add to, or delete tasks
from the strategy, and then return to activity 5.
Some agile teams conduct periodic “performance-only” scrums
or stand-ups when performance testing–related coordination, reporting, or analysis
is too time-consuming to be handled in the existing update structure. Whether
during a special “performance-only” scrum or stand-up or during existing sessions,
the team collectively makes most of the major adjustments to priorities,
strategies, tasks, and success criteria. Ensure that enough time is allocated
frequently enough for the team to make good performance-related decisions,
while changes are still easy to make.
The key to successfully implementing an agile performance-testing
approach is continual communication among team members. As described in the
previous steps, it is a good idea not only to communicate tasks and strategies
with all team members, checking back with one another frequently, but also to
plan time into testing schedules to review and update tasks and priorities.
The methods you use to communicate plans, strategies,
priorities, and changes are completely irrelevant as long as you are able to
adapt to changes without requiring significant rework, and as long as the team
continues to progress toward achieving the current performance-testing success
criteria.
Additional Considerations
Keep in mind the following additional considerations for
managing an agile performance test cycle:
- The best advice is to remember to communicate all
significant information and findings to the team.
- No matter how long or short the time between performance
builds, performance testing will always lag behind. Too many performance-testing
tasks take too long to develop and execute to keep up with development in real
time. Keep this in mind when setting priorities for what to performance-test
next. Choose wisely.
- Remember that for the vast majority of the development life
cycle, performance testing is about collecting useful information to
enhance performance through design, architecture, and development as it
happens. Comparisons against the end user–focused requirements and goals
only have meaning for customer review releases or production release
candidates. The rest of the time, you are looking for trends and obvious
problems, not pass/fail validation.
- Make use of existing unit-testing code for performance
testing at the component level. Doing so is quick, easy; helps the
developers detect trends in performance, and can make a powerful smoke
test.
- Do not force a performance build just because it is on the
schedule. If the current build is not appropriate for performance testing,
continue with what you have until it is appropriate, or give the
performance tester another task until something reasonable is ready.
- Performance testing is one of the single biggest catalysts
to significant changes in architecture, code, hardware, and environments.
Use this to your advantage by making observed performance issues highly
visible across the entire team. Simply reporting on performance every day
or two is not enough ― the team needs to read, understand, and react
to the reports, or else the performance testing loses much of its value.
Summary
Performance testing in an agile project environment allows you
to manage the testing in a highly flexible way. In particular, this approach
allows you to revisit the project vision and reprioritize tasks based on the
value they add to the performance test at a given point in time.