Performance Testing Guidance for Web Applications
J.D. Meier, Carlos Farre, Prashant Bansode, Scott Barber, and Dennis Rea
Microsoft Corporation
September 2007
Objectives
- Learn an approach to coordinating performance testing
within an iteration-based process.
- Learn how to detect and solve major issues early in the
project.
- Learn how to maximize flexibility without sacrificing
control.
- Learn how to provide managers and stakeholders with
progress and value indicators.
- Learn how to provide a structure for capturing information
that will not noticeably impact the release schedule.
- Learn how to apply an approach that is designed to embrace
change, not simply to tolerate it.
Overview
This chapter provides guidance for coordinating performance
testing with iteration-based processes that are found in Agile Software
Development, Extreme Programming (XP), the Rational Unified Process (RUP), and
other sources. The chapter describes the concepts underlying the activities
necessary to make performance testing successful within an iterative process,
as well as specific, actionable items that you can immediately apply to your
project in order to gain a significant return on this investment.
Performance testing is a critical aspect of many software
projects because it tests the architectural aspects of the customer experience
and provides an indication of overall software quality. Because it is
frequently expensive to set up and integrate performance testing, project teams
often wait until the end of the project development/test life cycle to do so.
The potential side effect to this approach is that when major issues are found
near the end of the development life cycle, it becomes much more expensive to
resolve them.
The key to working within an iteration-based work cycle is
team coordination. For this reason, the performance tester must be able to
adapt what he or she measures and analyzes per iteration cycle as circumstances
change.
How to Use This Chapter
Use this chapter to understand the activities involved in
performance testing in iterative development environments, and their
relationship with the core performance-testing activities. Also use this
chapter to understand what is accomplished during these activities. To get the most from this chapter:
- Use the “Iterative Performance Testing Activities”
section to get an overview of the core activities of performance
testing in iterative development environments, and as a quick reference
guide for you and your team.
- Use the various activity sections to understand the
details of the most critical performance-testing tasks.
- Additionally, use “Chapter 4 – Core Activities” to
understand the common core activities involved in successful
performance-testing projects. This will help you to apply the concepts
behind those activities to a particular approach to performance testing.
Introduction to the Approach
When viewed from a linear perspective, the approach starts
by examining the software development project as a whole, the reasons why
stakeholders have chosen to include performance testing in the project, and the
value that performance testing is expected to bring to the project. The results
of this examination include the team’s view of the success criteria for the
performance-testing effort.
Once the success criteria are understood at a high level, an
overall strategy is envisioned to guide the general approach to achieving those
criteria by summarizing what performance testing activities are anticipated to
add the most value at various points during the development life cycle. Those
points may include key project deliveries, checkpoints, sprints, iterations, or
weekly builds. For the purposes of this chapter, these events are collectively
referred to as “performance builds.” Frequently, while the strategy is
evolving, the performance specialist and/or the team will begin setting up a
performance-test environment and a load-generation environment.
With a strategy in mind and the necessary environments in
place, the test team draws up plans for major tests or tasks identified for
imminent performance builds. When a performance build is delivered, the plan’s tasks
should be executed in priority sequence (based on all currently available
information), appropriately reporting, recording, revising, reprioritizing,
adding, and removing tasks and improving the application and the overall plan
as the work progresses.
Iterative Performance Testing Activities
This approach can be represented by using the following nine
activities:
.gif)
Figure 5.1 Iterative Performance Testing
Activities
- Activity 1. Understand the Project Vision and Context.
The outcome of this activity is a shared understanding of the project
vision and context.
- Activity 2. Identify Reasons for Testing Performance.
Explicitly identify the reasons for performance testing.
- Activity 3. Identify the Value Performance Testing Adds
to the Project. Translate the project- and business-level objectives
into specific, identifiable, and manageable performance-testing
activities.
- Activity 4. Configure the Test Environment. Set up
the load-generation tools and the system under test, collectively known as
the performance test environment.
- Activity 5. Identify and Coordinate Tasks. Prioritize
and coordinate support, resources, and schedules to make the tasks
efficient and successful.
- Activity 6. Execute Task(s). Execute the
activities for the current iteration.
- Activity 7. Analyze Results and Report. Analyze
and share results with the team.
- Activity 8. Revisit Activities 1-3 and Consider
Performance Acceptance Criteria. Between iterations, ensure that the
foundational information has not changed. Integrate new information such
as customer feedback and update the strategy as necessary.
- Activity 9. Reprioritize Tasks. Based on the test
results, new information, and the availability of features and components,
reprioritize, add to, or delete tasks from the strategy, and then return
to activity 5.
Relationship to Core Performance Testing Activities
The following graphic displays how the seven core activities
described in Chapter 4 map to these nine activities:
.gif)
Figure 5.2 Relationship to Core Performance
Testing Activities
Activity 1. Understand the Project Vision and Context
The project vision and context are the foundation for
determining what performance testing activities are necessary and valuable.
Because the performance tester is not driving these items, the coordination
aspect refers more to team education about the performance implications of the
project vision and context, and to identifying areas where future coordination
will likely be needed for success.
A critical part of working with an iteration-based process
is asking the correct questions, providing the correct value, and performing
the correct task related to each step. Although situations can shift or add
more questions, values, or tasks, a sample checklist is provided as a starting
point for each step.
Checklist
Questions to ask:
- What are the performance implications of the project
vision?
- What are the performance implications of the service the
application is intended to provide, or what problem are we trying to solve
for the customer?
- How does the team envision performance testing as it
relates to the project schedule, structure, and available resources?
Value provided:
- Be involved in the product concept.
- Point out any areas of concern immediately.
- Point out assumptions related to available resources,
tools, and resource-monitoring instrumentation based on the project vision
and context as soon as they arise.
Tasks accomplished:
- Ask the whole team questions and provide answers.
- Determine the team’s perception of performance testing.
- Gain a conceptual understanding of the project’s critical
performance implications.
- Begin to define equipment and/or resources needed for
conducting performance testing.
- Understand resource constrains; for example, budget,
people, equipment.
- Understand how the team will coordinate.
- Understand how the team will communicate.
Coordinate with:
Activity 2. Identify Reasons for Testing Performance
The underlying reasons for testing performance on a
particular project are not always obvious based on the vision and context
alone. Project teams generally do not include performance testing as part of
the project unless there is some performance-related risk or concern they feel
needs to be mitigated. Explicitly identifying these risks and areas of concern is
the next fundamental step in determining what specific performance testing activities
will add the most value to the project.
Having a full-time performance tester on the team from the
start of the project may frequently be a good idea, but it does not happen
frequently. Generally, when a performance tester is present at project
inception, it means there is a specific, significant risk that the tester is
there to address.
Regardless of when a performance tester joins the team, once
the project vision and context are understood, it is worth taking the time to
verbalize and/or document the overall objectives of the performance-testing
effort based on the risks or concerns that the team has. The following
checklist should help you to accomplish this step.
Checklist
Questions to ask:
- What risk(s) is performance testing intended to mitigate
for this project?
- Are there specific contractual, compliance, or customer
performance expectations that are already known to be required?
- What performance concerns relating to this project already
exist?
Value provided:
- Be involved in the product concept.
- Point out any areas of concern immediately.
- Point out resource and instrumentation assumptions based
on the project vision and context when they arise.
- Guide the process of collecting/determining
performance-testing objectives.
- Capture implied usage scenarios of particular performance
concerns.
- Capture implied performance goals, requirements, targets,
and thresholds as they come up in conversation.
Tasks accomplished:
- Ask the whole team questions and provide answers.
- Determine the project-level objectives for conducting
performance testing.
- Refine estimates of equipment and/or resources required
for conducting performance testing.
- Identify disconnects between the objectives of the
performance-testing effort and the equipment and resources to be made
available.
- Capture implied performance goals, requirements, targets,
and thresholds to be fleshed out later.
- Capture implied usage scenarios of particular concern to
be fleshed out later.
Coordinate with:
Activity 3. Identify the Value Performance Testing Adds to the Project
Using information gained from activities 1 and 2, you can
now clarify the value added through performance testing, and convert that value
into a conceptual performance-testing strategy. The point is to translate the
project- and business-level objectives into specific, identifiable, and
manageable performance-testing activities. The coordination aspect of this step
involves team-wide discussion and agreement on which performance-testing
activities are likely to add value or provide valuable information, and if
these activities are worth planning for at this time.
Checklist
Questions to ask:
- What performance-testing activities will help achieve the
performance-testing objectives?
- What performance-testing activities are needed to validate
any contractual, compliance, project, or customer performance criteria or
expectations that are known at this time?
- What performance-testing activities will help address
currently known performance concerns?
Value provided:
- Ensure team-wide support of performance-testing
activities.
- Ensure that the team has adequate warning about
performance-testing activities that will require the support of additional
team members.
- Determine if resource and instrumentation assumptions are
adequate.
- Guide the process of determining how performance-testing
objectives will be measured.
- Capture additional implied usage scenarios of particular
performance concerns.
- Capture additional implied performance goals,
requirements, targets, and thresholds as they come up in conversation.
Tasks accomplished:
- Ask the whole team questions and provide answers.
- Determine a conceptual project-level strategy for
determining if the objectives for conducting performance testing have been
met.
- Refine estimates of equipment and/or resources required
for conducting performance testing.
- Identify disconnects between the objectives of the
performance-testing effort and the equipment and resources to be made
available.
- Capture additional implied performance goals,
requirements, targets, and thresholds to be fleshed out later.
- Capture additional implied usage scenarios of particular
concern to be fleshed out later.
Coordinate with:
Activity 4. Configure the Test Environment
With a conceptual strategy in place, prepare the tools and
resources in order to execute the strategy as features and components become
available for test. Take this step as soon as possible, so that the team has
this resource from the beginning.
This step is fairly straightforward. Set up the load-generation
tools and the system under test — collectively known as the performance test
environment — and ensure that this environment will meet engineering needs. The
coordination component of this step typically involves asking managers and
administrators to obtain and/or configure equipment and other resources that
are not under the direct control of the team or performance tester.
Checklist
Questions to ask:
- Who administrates the performance-testing environment of
the application under test?
- Who administrates the load-generation tool/environment?
- Who configures and operates resource monitors for the
application under test?
- Is special permission needed prior to generating load of a
certain volume?
- Who can reset the application under test?
- What other components require special coordination?
- What security or authentication considerations are there
for simulating multiple users?
- What coordination needs to be done to enable the use of recording
and/or monitoring software?
Value provided:
- Ensure that the load-generation and performance-test
environments are ready when the team needs them.
- Ensure that the entire team knows who to contact for help
with performance-testing environment support.
- Ensure that performance testing support staff knows what
they are supporting.
Tasks accomplished:
- Performance-test environment configured and ready to begin
testing.
- Load-generation environment configured and ready to begin
testing.
- Support responsibilities assigned.
- Special permissions, time of day for high load tests,
etc., determined.
Coordinate with:
- System administrators
- Network support
- Database administrators
- Infrastructure support
- Managers of those above
- Development team
Activity 5. Identify and Coordinate Tasks
Performance testing tasks do not happen in isolation. The
performance specialist needs to work with the team to prioritize and coordinate
support, resources, and schedules to make the tasks efficient and successful.
During the pre-iteration planning meeting, look at where the
project is now and where you want to be to determine what should and can be
done next. When planning for the iteration cycle, the performance tester is
driven by the goals that have been determined for this cycle. This step also
includes signing up for the activities that will be accomplished during this
cycle.
Checklist
Questions to ask:
- What is the performance goal for this cycle?
- Where is the project in terms of the overall project
performance goals?
- Has the system achieved all of its performance objectives?
- Has tuning been accomplished since the last iteration?
- What analysis, reports, or retesting will add value during
this iteration?
- Who requires pairing in order to do performance testing?
- How much time is available?
- How much time does each task take?
- What is the most critical activity?
Value provided:
- Provide insight on how the overall project is achieving
its goal.
- Provide insight on what can be measured and reported on in
this cycle.
- Provide insight on any critical issues that may have
arisen from the last iteration cycle.
- Make suggestions to other team members.
- Transfer lessons learned as they emerge from the test.
- Pair with developers to improve performance unit testing.
- Help reuse unit tests.
- Help reuse functional tests.
Tasks accomplished:
- Estimate how much work is achievable.
- Determine if anyone needs to be paired out.
- Prioritize achievable work.
- Identify primary and alternate tasks for this cycle.
Coordinate with:
- Managers and stakeholders
- Developers and administrators
- Infrastructure and test environment support
- Users or user representatives
Activity 6. Execute Task(s)
Conduct tasks in one- to two-day segments. See them through
to completion, but be willing to take important detours along the way if an
opportunity to add additional value presents itself. Step 5 defines what work
the team members will sign up for in this iteration. Now it is time to execute
the activities for this iteration.
Checklist
Questions to ask:
- Have recent test results or project updates made this task
more or less valuable compared to other tests we could be conducting right
now?
- What additional team members should be involved with this
task?
- Are there other important tasks that can be conducted in
parallel with this one?
- Do the preliminary results make sense?
- Is the test providing the data we expected?
Value provided:
- Evaluate algorithm efficiency.
- Monitor resource usage trends.
- Measure response times.
- Collect data for scalability and capacity planning.
- Transfer lessons learned as they emerge from the test.
- Improve performance unit testing by pairing performance
testers with developers.
- Help reuse unit tests.
- Help reuse functional tests.
Tasks accomplished:
- Conduct tests.
- Collect data.
- Validate test assumptions and techniques.
- Potentially tune while testing.
- Pair with other team members; this does not mean only
working with a developer or tester but can also mean working with a writer
to capture his or her understanding of how the system performance works,
or working with the customer directly.
Coordinate with:
- Developers and administrators
- Infrastructure and test environment support
- Users or user representatives
- Managers and stakeholders
- Other performance testers who are not on the project
Activity 7. Analyze Results and Report
To keep up with an iterative process, results need to be
analyzed and shared quickly. If the analysis is inconclusive, retest at the
earliest possible opportunity to give the team maximum time to react to
performance issues. As the project is wrapped for final shipping, it is usually
worth having a meeting afterward to collect and pass along lessons learned. In
most cases it is valuable to have a daily or every-other-day update to share
information and coordinate next tasks.
Checklist
Questions to ask:
- Do the preliminary results make sense?
- Is the test providing the data we expected?
- Is the data valuable?
- Are more tests required to derive meaning from the data?
- Is tuning required? If so, do we know what to tune?
- Do the results indicate that there are additional tests
that we need to execute that have not been planned for?
- Do the results indicate that any of the tests we are
planning to conduct are no longer necessary?
- Have any performance objectives been met?
- Have any performance objectives been rendered obsolete?
Value provided:
- Evaluate algorithm efficiency.
- Monitor resource usage trends.
- Measure response times.
- Collect data for scalability and capacity planning.
- Transfer lessons learned as they emerge from the test.
Tasks accomplished:
- Analyze data collaboratively.
- Determine the meaning of the results.
- Share data with the whole team.
- Import lessons learned into future iteration planning.
Coordinate with:
- Developers and administrators
- Managers and stakeholders
- Users or user representatives
- Other performance testers who are not on the project
Activity 8. Revisit Activities 1-3 and Consider Performance Acceptance
Criteria
Between iterations, ensure that the foundational information
has not changed. Integrate new information, such as customer feedback, and
update the strategy as necessary.
Checklist
Questions to ask:
- Have the performance implications of the project vision
changed?
- Have the performance implications of the service we are
trying to provide changed, or has the problem we are trying to solve for
the customer changed?
- Have the project schedule, structure, or available
resources changed?
- Have the performance-testing objectives changed?
- Have the performance-testing activities needed to validate
any contractual, compliance, project, or customer performance criteria or
expectations changed?
- What performance-testing activities will help address
currently known performance concerns?
Value provided:
- Update resource and instrumentation assumptions and needs.
- Point out any areas of concern.
- Point out resource and instrumentation needs and/or risks.
- Update performance-testing objectives.
- Enhance and update usage scenarios of particular
performance concerns.
- Enhance and update performance goals, requirements,
targets, and thresholds.
- Ensure that the team has adequate warning about upcoming
performance-testing activities that will require the support of additional
team members.
Tasks accomplished:
- Enhance and update understanding of the project’s critical
performance implications.
- Update resource constraints; for example, budget, people,
and equipment.
- Update/improve how the team will coordinate.
- Update/improve how the team will communicate.
- Revise performance-testing strategy.
- Refine estimates of equipment and/or resources required
for conducting performance testing.
- Identify incompatibilities or conflicts between the
objectives of the performance-testing effort and the equipment and
resources to be made available.
- Capture additional performance goals, requirements,
targets, and thresholds.
- Capture additional usage scenarios of particular concern.
- Report current performance-testing status.
Coordinate with:
Activity 9. Reprioritize Tasks
Based on the test results, new information, and the
availability of features and components, reprioritize, add to, or delete tasks
from the strategy, and then return to activity 5.
Checklist
Questions to ask:
- What performance-testing activities will help address
currently known performance concerns?
- What is the performance goal for this cycle?
- Where is the project in terms of the overall project
performance goals?
- Has the system achieved all of its performance objectives?
- Has tuning been accomplished since the last iteration?
- What analysis, reports, or retesting will add value during
this iteration cycle?
- Who requires pairing to do performance testing?
- How much time is available?
- How much time does each task take?
- What is the most critical activity?
Value provided:
- Provide insight on how the overall project is achieving
its goal.
- Provide insight on what can be measured and reported on in
this cycle.
- Provide insight on any critical issues that may have
arisen from the last iteration.
- Make suggestions to other team members.
- Transfer lessons learned as they emerge from the test.
- Pair with developers to improve performance unit testing.
- Help reuse unit tests.
- Help reuse functional tests.
Tasks accomplished:
- Report current performance-testing status.
- Estimate how much work is achievable.
- Determine if anyone needs to be paired out.
- Prioritize achievable work.
- Identify primary and alternate tasks for this cycle.
Coordinate with:
- Managers and stakeholders
- Developers and administrators
- Infrastructure and test environment support
- Users or user representatives
Summary
Performance testing with iteration-based processes is a
common practice in development cycles such as Agile, XP, RUP, and other
sources. To be effective, performance testing should be managed correctly in
the context of iteration planning and processes.