Performance Testing Guidance for Web Applications
J.D. Meier, Carlos Farre, Prashant Bansode, Scott Barber, and Dennis Rea
Microsoft Corporation
September 2007
Objectives
- Learn the seven core activities that are integral to the
majority of performance-testing projects.
- Understand the seven core activities in sufficient detail
to identify how your tasks and processes map to these activities.
- Understand various performance-testing approaches that can
be built around the core activities.
Overview
This chapter provides a high-level introduction to the most
common core activities involved in performance-testing your applications and
the systems that support those applications. Performance testing is a complex
activity that cannot effectively be shaped into a “one-size-fits-all” or even a
“one-size-fits-most” approach. Projects, environments, business drivers,
acceptance criteria, technologies, timelines, legal implications, and available
skills and tools simply make any notion of a common, universal approach
unrealistic.
That said, there are some activities that are part of nearly
all project-level performance-testing efforts. These activities may occur at
different times, be called different things, have different degrees of focus,
and be conducted either implicitly or explicitly, but when all is said and
done, it is quite rare when a performance-testing-project does not involve at
least making a decision around the seven core activities identified and
referenced throughout this guide. These seven core activities do not in
themselves constitute an approach to performance testing; rather, they
represent the foundation upon which an approach can be built that is
appropriate for your project.
How to Use This Chapter
Use this chapter to understand the core activities of
performance testing and what these activities accomplish. To get
the most from this chapter:
- Use the “Summary Table of Core Performance
Activities” section to get an overview of the core activities of
performance testing, and as quick reference guide for you and your team.
- Use the various Activity sections to understand the
details of the most critical performance-testing tasks, as well as
considerations for each activity.
Overview of Activities
The following sections discuss the seven activities that most
commonly occur across successful performance-testing projects. The key to effectively
implementing these activities is not when you conduct them, what you call them,
whether or not they overlap, or the iteration pattern among them, but rather
that you understand and carefully consider the concepts, applying them in the
manner that is most valuable to your own project context.
Starting with at least a cursory knowledge of the project context,
most teams begin identifying the test environment and the performance
acceptance criteria more or less in parallel. This is due to the fact that all
of the remaining activities are affected by the information gathered in
activities 1 and 2. Generally, you will revisit these activities periodically
as you and your team learn more about the application, its users, its features,
and any performance-related risks it might have.
Once you have a good enough understanding of the project
context, the test environment, and the performance acceptance criteria, you
will begin planning and designing performance tests and configuring the test
environment with the tools needed to conduct the kinds of performance tests and
collect the kinds of data that you currently anticipate needing, as described
in activities 3 and 4. Once again, in most cases you will revisit these
activities periodically as more information becomes available.
With at least the relevant aspects of activities 1 through 4
accomplished, most teams will move into an iterative test cycle (activities
5-7) where designed tests are implemented by using some type of load-generation
tool, the implemented tests are executed, and the results of those tests are
analyzed and reported in terms of their relation to the components and features
available to test at that time.
To the degree that performance testing begins before the
system or application to be tested has been completed, there is a naturally
iterative cycle that results from testing features and components as they
become available and continually gaining more information about the
application, its users, its features, and any performance-related risks that
present themselves via testing.
Summary Table of Core Performance-Testing Activities
The following table summarizes the seven core
performance-testing activities along with the most common input and output for
each activity. Note that project context is not listed, although it is a
critical input item for each activity.
|
Activity
|
Input
|
Output
|
|
Activity 1. Identify the Test Environment
|
- Logical and physical production architecture
- Logical and physical test architecture
- Available tools
|
- Comparison of test and production environments
- Environment-related concerns
- Determination of whether additional tools are required
|
|
Activity 2. Identify Performance Acceptance Criteria
|
- Client expectations
- Risks to be mitigated
- Business requirements
- Contractual obligations
|
- Performance-testing success criteria
- Performance goals and requirements
- Key areas of investigation
- Key performance indicators
- Key business indicators
|
|
Activity 3. Plan and Design Tests
|
- Available application features and/or components
- Application usage scenarios
- Unit tests
- Performance acceptance criteria
|
- Conceptual strategy
- Test execution prerequisites
- Tools and resources required
- Application usage models to be simulated
- Test data required to implement tests
- Tests ready to be implemented
|
|
Activity 4. Configure the Test Environment
|
- Conceptual strategy
- Available tools
- Designed tests
|
- Configured load-generation and resource-monitoring tools
- Environment ready for performance testing
|
|
Activity 5. Implement the Test Design
|
- Conceptual strategy
- Available tools/environment
- Available application features and/or components
- Designed tests
|
- Validated, executable tests
- Validated resource monitoring
- Validated data collection
|
|
Activity 6. Execute the Test
|
- Task execution plan
- Available tools/environment
- Available application features and/or components
- Validated, executable tests
|
|
|
Activity 7. Analyze Results, Report, and Retest
|
- Task execution results
- Performance acceptance criteria
- Risks, concerns, and issues
|
- Results analysis
- Recommendations
- Reports
|
Core Performance-Testing Activities Walkthrough
The seven core performance-testing activities can be
summarized as follows.
.gif)
Figure 4.1 Core Performance Testing
Activities
- Activity 1. Identify the Test Environment. Identify
the physical test environment and the production environment as well as
the tools and resources available to the test team. The physical
environment includes hardware, software, and network configurations. Having
a thorough understanding of the entire test environment at the outset
enables more efficient test design and planning and helps you identify
testing challenges early in the project. In some situations, this process
must be revisited periodically throughout the project’s life cycle.
- Activity 2. Identify Performance Acceptance Criteria.
Identify the response time, throughput, and resource utilization goals and
constraints. In general, response time is a user concern, throughput is a
business concern, and resource utilization is a system concern.
Additionally, identify project success criteria that may not be captured
by those goals and constraints; for example, using performance tests to
evaluate what combination of configuration settings will result in the
most desirable performance characteristics.
- Activity 3. Plan and Design Tests. Identify key
scenarios, determine variability among representative users and how to
simulate that variability, define test data, and establish metrics to be
collected. Consolidate this information into one or more models of system
usage to be implemented, executed, and analyzed.
- Activity 4. Configure the Test Environment.
Prepare the test environment, tools, and resources necessary to execute
each strategy as features and components become available for test. Ensure
that the test environment is instrumented for resource monitoring as
necessary.
- Activity 5. Implement the Test Design. Develop the
performance tests in accordance with the test design.
- Activity 6. Execute the Test. Run and monitor your
tests. Validate the tests, test data, and results collection. Execute
validated tests for analysis while monitoring the test and the test
environment.
- Activity 7. Analyze Results, Report, and Retest.
Consolidate and share results data. Analyze the data both individually and
as a cross-functional team. Reprioritize the remaining tests and
re-execute them as needed. When all of the metric values are within
accepted limits, none of the set thresholds have been violated, and all of
the desired information has been collected, you have finished testing that
particular scenario on that particular configuration.
Activity 1. Identify the Test Environment
The environment in which your performance tests will be
executed, along with the tools and associated hardware necessary to execute the
performance tests, constitute the test environment. Under ideal conditions, if
the goal is to determine the performance characteristics of the application in
production, the test environment is an exact replica of the production
environment but with the addition of load-generation and resource-monitoring
tools. Exact replicas of production environments are uncommon.
The degree of similarity between the hardware, software, and
network configuration of the application under test conditions and under actual
production conditions is often a significant consideration when deciding what
performance tests to conduct and what size loads to test. It is important to
remember that it is not only the physical and software environments that impact
performance testing, but also the objectives of the test itself. Often,
performance tests are applied against a proposed new hardware infrastructure to
validate the supposition that the new hardware will address existing
performance concerns.
The key factor in identifying your test environment is to
completely understand the similarities and differences between the test and
production environments. Some critical factors to consider are:
- Hardware
- Configurations
- Machine hardware (processor, RAM, etc.)
- Network
- Network architecture and end-user location
- Load-balancing implications
- Cluster and Domain Name System (DNS) configurations
- Tools
- Load-generation tool limitations
- Environmental impact of monitoring tools
- Software
- Other software installed or running in shared or virtual
environments
- Software license constraints or differences
- Storage capacity and seed data volume
- Logging levels
- External factors
- Volume and type of additional traffic on the network
- Scheduled or batch processes, updates, or backups
- Interactions with other systems
Considerations
Consider the following key points when characterizing the
test environment:
- Although few performance testers install, configure, and
administrate the application being tested, it is beneficial for the
testers to have access to the servers and software, or to the administrators
who do.
- Identify the amount and type of data the application must
be seeded with to emulate real-world conditions.
- Identify critical system components. Do any of the system
components have known performance concerns? Are there any integration
points that are beyond your control for testing?
- Get to know the IT staff. You will likely need their
support to perform tasks such as monitoring overall network traffic and
configuring your load-generation tool to simulate a realistic number of Internet
Protocol (IP) addresses.
- Check the configuration of load balancers.
- Validate name resolution with DNS. This may account for
significant latency when opening database connections.
- Validate that firewalls, DNS, routing, and so on treat the
generated load similarly to a load that would typically be encountered in
a production environment.
- It is often appropriate to have systems administrators set
up resource-monitoring software, diagnostic tools, and other utilities in
the test environment.
Activity 2. Identify Performance Acceptance Criteria
It generally makes sense to start identifying, or at least
estimating, the desired performance characteristics of the application early in
the development life cycle. This can be accomplished most simply by noting the
performance characteristics that your users and stakeholders equate with good
performance. The notes can be quantified at a later time.
Classes of characteristics that
frequently correlate to a user’s or stakeholder’s satisfaction typically include:
- Response time. For example, the product catalog
must be displayed in less than three seconds.
- Throughput. For example, the system must
support 25 book orders per second.
- Resource utilization. For example, processor
utilization is not more than 75 percent. Other important resources that
need to be considered for setting objectives are memory, disk input/output
(I/O), and network I/O.
Considerations
Consider the following key points when identifying
performance criteria:
- Business requirements
- User expectations
- Contractual obligations
- Regulatory compliance criteria and industry standards
- Service Level Agreements (SLAs)
- Resource utilization targets
- Various and diverse, realistic workload models
- The entire range of anticipated load conditions
- Conditions of system stress
- Entire scenarios and component activities
- Key performance indicators
- Previous releases of the application
- Competitor’s applications
- Optimization objectives
- Safety factors, room for growth, and scalability
- Schedule, staffing, budget, resources, and other
priorities
Activity 3. Plan and Design Tests
Planning and designing performance tests involves identifying
key usage scenarios, determining appropriate variability across users,
identifying and generating test data, and specifying the metrics to be
collected. Ultimately, these items will provide the foundation for workloads
and workload profiles.
When designing and planning tests with the intention of
characterizing production performance, your goal should be to create real-world
simulations in order to provide reliable data that will enable your
organization to make informed business decisions. Real-world test designs will
significantly increase the relevancy and usefulness of results data.
Key usage scenarios for the application typically surface during
the process of identifying the desired performance characteristics of the
application. If this is not the case for your test project, you will need to
explicitly determine the usage scenarios that are the most valuable to script.
Consider the following when identifying key usage scenarios:
- Contractually obligated usage scenario(s)
- Usage scenarios implied or mandated by performance-testing
goals and objectives
- Most common usage scenario(s)
- Business-critical usage scenario(s)
- Performance-intensive usage scenario(s)
- Usage scenarios of technical concern
- Usage scenarios of stakeholder concern
- High-visibility usage scenarios
When identified, captured, and reported correctly, metrics
provide information about how your application’s performance compares to your
desired performance characteristics. In addition, metrics can help you identify
problem areas and bottlenecks within your application.
It is useful to identify the metrics related to the
performance acceptance criteria during test design so that the method of
collecting those metrics can be integrated into the tests when implementing the
test design. When identifying metrics, use either specific desired
characteristics or indicators that are directly or indirectly related to those
characteristics.
Considerations
Consider the following key points when planning and
designing tests:
- Realistic test designs are sensitive to dependencies
outside the control of the system, such as humans, network activity, and
other systems interacting with the application.
- Realistic test designs are based on what you expect to
find in real-world use, not theories or projections.
- Realistic test designs produce more credible results and
thus enhance the value of performance testing.
- Component-level performance tests are integral parts of realistic
testing.
- Realistic test designs can be more costly and
time-consuming to implement, but they provide far more accuracy for the
business and stakeholders.
- Extrapolating performance results from unrealistic tests
can create damaging inaccuracies as the system scope increases, and
frequently lead to poor decisions.
- Involve the developers and administrators in the process
of determining which metrics are likely to add value and which method best
integrates the capturing of those metrics into the test.
- Beware of allowing your tools to influence your test
design. Better tests almost always result from designing tests on the
assumption that they can be executed and then adapting the test or the
tool when that assumption is proven false, rather than by not
designing particular tests based on the assumption that you do not have
access to a tool to execute the test.
Realistic test designs include:
- Realistic simulations of user delays and think times,
which are crucial to the accuracy of the test.
- User abandonment, if users are likely to abandon a task
for any reason.
- Common user errors.
Activity 4. Configure the Test Environment
Preparing the test environment, tools, and resources for
test design implementation and test execution prior to features and components
becoming available for test can significantly increase the amount of testing
that can be accomplished during the time those features and components are
available.
Load-generation and application-monitoring tools are almost
never as easy to get up and running as one expects. Whether issues arise from
setting up isolated network environments, procuring hardware, coordinating a
dedicated bank of IP addresses for IP spoofing, or version compatibility
between monitoring software and server operating systems, issues always seem to
arise from somewhere. Start early, to ensure that issues are resolved before
you begin testing.
Additionally, plan to periodically reconfigure, update, add
to, or otherwise enhance your load-generation environment and associated tools
throughout the project. Even if the application under test stays the same and
the load-generation tool is working properly, it is likely that the metrics you
want to collect will change. This frequently implies some degree of change to,
or addition of, monitoring tools.
Considerations
Consider the following key points when configuring the test
environment:
- Determine how much load you can generate before the load
generators reach a bottleneck. Typically, load generators encounter bottlenecks
first in memory and then in the processor.
- Although it may seem like a commonsense practice, it is
important to verify that system clocks are synchronized on all of the
machines from which resource data will be collected. Doing so can save you
significant time and prevent you from having to dispose of the data
entirely and repeat the tests after synchronizing the system clocks.
- Validate the accuracy of load test execution against
hardware components such as switches and network cards. For example,
ensure the correct full-duplex mode operation and correct emulation of
user latency and bandwidth.
- Validate the accuracy of load test execution related to
server clusters in load-balanced configuration. Consider using load-testing
techniques to avoid affinity of clients to servers due to their using the same
IP address. Most load-generation tools offer the ability to simulate usage
of different IP addresses across load-test generators.
- Monitor resource utilization (CPU, network, memory, disk
and transactions per time) across servers in the load-balanced
configuration during a load test to validate that the load is distributed.
Activity 5. Implement the Test Design
The details of creating an executable performance test are
extremely tool-specific. Regardless of the tool that you are using, creating a
performance test typically involves scripting a single usage scenario and then
enhancing that scenario and combining it with other scenarios to ultimately
represent a complete workload model.
Load-generation tools inevitably lag behind evolving
technologies and practices. Tool creators can only build in support for the
most prominent technologies and, even then, these have to become prominent
before the support can be built. This often means that the biggest challenge involved
in a performance-testing project is getting your first relatively realistic
test implemented with users generally being simulated in such a way that the
application under test cannot legitimately tell the difference between the
simulated users and real users. Plan for this and do not be surprised when it
takes significantly longer than expected to get it all working smoothly.
Considerations
Consider the following key points when implementing the test
design:
- Ensure that test data feeds are implemented correctly.
Test data feeds are data repositories in the form of databases, text
files, in-memory variables, or spreadsheets that are used to simulate
parameter replacement during a load test. For example, even if the
application database test repository contains the full production set,
your load test might only need to simulate a subset of products being
bought by users due to a scenario involving, for example, a new product or
marketing campaign. Test data feeds may be a subset of production data
repositories.
- Ensure that application data feeds are implemented correctly
in the database and other application components. Application data feeds
are data repositories, such as product or order databases, that are consumed
by the application being tested. The key user scenarios, run by the load
test scripts may consume a subset of this data.
- Ensure that validation of transactions is implemented
correctly. Many transactions are reported successful by the Web server,
but they fail to complete correctly. Examples of validation are, database
entries inserted with correct number of rows, product information being
returned, correct content returned in html data to the clients etc.
- Ensure hidden fields or other special data are handled
correctly. This refers to data returned by Web server that needs to be
resubmitted in subsequent request, like session IDs or product ID that
needs to be incremented before passing it to the next request.
- Validate the monitoring of key performance indicators
(KPIs).
- Add pertinent indicators to facilitate articulating
business performance.
- If the request accepts parameters, ensure that the
parameter data is populated properly with variables and/or unique data to
avoid any server-side caching.
- If the tool does not do so automatically, consider adding
a wrapper around the requests in the test script in order to measure the
request response time.
- It is generally worth taking the time to make the script
match your designed test, rather than changing the designed test to save
scripting time.
- Significant value can be gained from evaluating the output
data collected from executed tests against expectations in order to test
or validate script development.
Activity 6. Execute the Test
Executing tests is what most people envision when they think
about performance testing. It makes sense that the process, flow, and technical
details of test execution are extremely dependent on your tools, environment,
and project context. Even so, there are some fairly universal tasks and
considerations that need to be kept in mind when executing tests.
Much of the performance testing–related training available
today treats test execution as little more than starting a test and monitoring
it to ensure that the test appears to be running as expected. In reality, this
activity is significantly more complex than just clicking a button and
monitoring machines.
Test execution can be viewed as a combination of the
following sub-tasks:
- Coordinate test execution and monitoring with the team.
- Validate tests, configurations, and the state of the
environments and data.
- Begin test execution.
- While the test is running, monitor and validate scripts,
systems, and data.
- Upon test completion, quickly review the results for
obvious indications that the test was flawed.
- Archive the tests, test data, results, and other
information necessary to repeat the test later if needed.
- Log start and end times, the name of the result data, and
so on. This will allow you to identify your data sequentially after your
test is done.
As you prepare to begin test execution, it is worth taking the
time to double-check the following items:
- Validate that the test environment matches the
configuration that you were expecting and/or designed your test for.
- Ensure that both the test and the test environment are
correctly configured for metrics collection.
- Before running the real test, execute a quick smoke test
to make sure that the test script and remote performance counters are
working correctly. In the context of performance testing, a smoke test
is designed to determine if your application can successfully perform all
of its operations under a normal load condition for a short time.
- Reset the system (unless your scenario calls for doing
otherwise) and start a formal test execution.
- Make sure that the test scripts’ execution represents the
workload model you want to simulate.
- Make sure that the test is configured to collect the key
performance and business indicators of interest at this time.
Considerations
Consider the following key points when executing the test:
- Validate test executions for data updates, such as orders
in the database that have been completed.
- Validate if the load-test script is using the correct data
values, such as product and order identifiers, in order to realistically simulate
the business scenario.
- Whenever possible, limit test execution cycles to one to
two days each. Review and reprioritize after each cycle.
- If at all possible, execute every test three times. Note
that the results of first-time tests can be affected by loading Dynamic-Link
Libraries (DLLs), populating server-side caches, or initializing scripts
and other resources required by the code under test. If the results of the
second and third iterations are not highly similar, execute the test
again. Try to determine what factors account for the difference.
- Observe your test during execution and pay close attention
to any behavior you feel is unusual. Your instincts are usually right, or
at least valuable indicators.
- No matter how far in advance a test is scheduled, give the
team 30-minute and 5-minute warnings before launching the test (or
starting the day’s testing) if you are using a shared test environment.
Additionally, inform the team whenever you are not going to be executing
for more than one hour in succession so that you do not impede the
completion of their tasks.
- Do not process data, write reports, or draw diagrams on
your load-generating machine while generating a load, because this can
skew the results of your test.
- Turn off any active virus-scanning on load-generating
machines during testing to minimize the likelihood of unintentionally
skewing the results of your test.
- While load is being generated, access the system manually
from a machine outside of the load-generation environment during test
execution so that you can compare your observations with the results data
at a later time.
- Remember to simulate ramp-up and cool-down periods
appropriately.
- Do not throw away the first iteration because of
application script compilation, Web server cache building, or other
similar reasons. Instead, measure this iteration separately so that you
will know what the first user after a system-wide reboot can expect.
- Test execution is never really finished, but eventually
you will reach a point of diminishing returns on a particular test. When
you stop obtaining valuable information, move on to other tests.
- If you feel you are not making progress in understanding
an observed issue, it may be more efficient to eliminate one or more
variables or potential causes and then run the test again.
Activity 7. Analyze Results, Report, and Retest
Managers and stakeholders need more than just the results
from various tests — they need conclusions, as well as consolidated data that
supports those conclusions. Technical team members also need more than just
results — they need analysis, comparisons, and details behind how the results
were obtained. Team members of all types get value from performance results
being shared more frequently.
Before results can be reported, the data must be analyzed.
Consider the following important points when analyzing the data returned by
your performance test:
- Analyze the data both individually and as part of a
collaborative, cross-functional technical team.
- Analyze the captured data and compare the results against
the metric’s acceptable or expected level to determine whether the
performance of the application being tested shows a trend toward or away
from the performance objectives.
- If the test fails, a diagnosis and tuning activity are generally
warranted.
- If you fix any bottlenecks, repeat the test to validate
the fix.
- Performance-testing results will often enable the team to
analyze components at a deep level and correlate the information back to
the real world with proper test design and usage analysis.
- Performance test results should enable informed
architecture and business decisions.
- Frequently, the analysis will reveal that, in order to
completely understand the results of a particular test, additional metrics
will need to be captured during subsequent test-execution cycles.
- Immediately share test results and make raw data available
to your entire team.
- Talk to the consumers of the data to validate that the
test achieved the desired results and that the data means what you think
it means.
- Modify the test to get new, better, or different
information if the results do not represent what the test was defined to
determine.
- Use current results to set priorities for the next test.
- Collecting metrics frequently produces very large volumes
of data. Although it is tempting to reduce the amount of data, always
exercise caution when using data-reduction techniques because valuable
data can be lost.
Most reports fall into one of the following two categories:
- Technical Reports
- Description of the test, including workload model and
test environment.
- Easily digestible data with minimal pre-processing.
- Access to the complete data set and test conditions.
- Short statements of observations, concerns, questions,
and requests for collaboration.
- Stakeholder Reports
- Criteria to which the results relate.
- Intuitive, visual representations of the most relevant
data.
- Brief verbal summaries of the chart or graph in terms of
criteria.
- Intuitive, visual representations of the workload model
and test environment.
- Access to associated technical reports, complete data
sets, and test conditions.
- Summaries of observations, concerns, and recommendations.
The key to effective reporting is to present information of
interest to the intended audience in a manner that is quick, simple, and
intuitive. The following are some underlying principles for achieving effective
reports:
- Report early, report often.
- Report visually.
- Report intuitively.
- Use the right statistics.
- Consolidate data correctly.
- Summarize data effectively.
- Customize for the intended audience.
- Use concise verbal summaries using strong but factual
language.
- Make the data available to stakeholders.
- Filter out any unnecessary data.
- If reporting intermediate results, include the priorities,
concerns, and blocks for the next several test-execution cycles.
Summary
Performance testing involves a set of common core activities
that occur at different stages of projects. Each activity has specific
characteristics and tasks to be accomplished. These activities have been found
to be present — or at least to have been part of an active, risk-based decision
to omit one of the activities — in every deliberate and successful performance-testing
project that the authors and reviewers have experienced. It is important to
understand each activity in detail and then apply the activities in a way that
best fits the project context.