Team Development with Visual Studio Team Foundation Server
J.D. Meier, Jason Taylor, Prashant Bansode, Alex Mackman, and Kevin Jones
Microsoft Corporation
September 2007
Applies To
- Microsoft® Visual Studio® 2005 Team Foundation Server
(TFS)
- Microsoft Visual Studio Team System (VSTS)
Summary
This How To article walks you through the process of initiating
new software development projects by creating and configuring new team projects
based on a selected template and shows you how to use TFS tools to manage,
control and monitor the ongoing software development processes throughout the
software development lifecycle.
Contents
- Objective
- Overview
- Summary of Steps
- Before You Begin
- Step 1 – Choose a Process Template
- Step 2 – Create a Team Project
- Step 3 – Create Security Groups (Optional)
- Step 4 – Add Team Members in Team Foundation Server
- Step 5 – Determine Your Iteration Cycle
- Step 6 – Capture Your Project Scenarios in TFS
- Step 7 – Identify the Scenarios for the Iteration
- Step 8 – Define Your Quality of Service Requirements
- Step 9 – Plan Your Iteration
- Step 10 – Monitor Progress
- Area and Iteration Consideration
- Additional Resources
Objective
- Learn how to create team projects in TFS
- Learn how to manage projects in TFS
Overview
Visual Studio Team System provides tools and reports to help
project managers control and support the entire software development life cycle
in a unified and centralized manner. By controlling the software process
directly through VSTS and a centralized database shared by all team members,
team communication is improved, and handoffs required between team members are
automated. In addition using reports driven from the TFS data warehouse makes
it much easier to monitor and track project progress.
This How To article walks you through the process of managing
a team project from the first steps of creating and configuring a new project
and then through the steps required to monitor the progress of an ongoing
project.
Summary of Steps
- Step 1 – Choose a Process Template
- Step 2 – Create a Team Project
- Step 3 – Create Security Groups (Optional)
- Step 4 – Add Team Members in Team Foundation Server
- Step 5 – Determine Your Iteration Cycle
- Step 6 – Capture Your Project Scenarios in TFS
- Step 7 – Identify the Scenarios for the Iteration
- Step 8 – Define Your Quality of Service Requirements
- Step 9 – Plan Your Iteration
- Step 10 – Monitor Progress.
Before You Begin
Before you start creating a new team project, you should
gather the following information:
- The process you want to use for the project. The
process you want to use to manage your project determines the template you
should select when creating a new team project. It also helps you evaluate
the degree to which you should customize the supplied templates. If you
favor an agile style of project execution, start by selecting the Microsoft
Solutions Framework (MSF) for Agile Software Development (MSF Agile) template
and then consider any customizations you might need.
- The project name. Give careful consideration to the
naming convention that you use for the team projects you create. Make sure
that your project names are sufficiently unique and use names that enable
other people to easily find the project. Some organizations use project
codes as part of their names, while others might use a combination of
department and project title.
- Source control structure. Consider whether you need
to start with an empty source control tree or whether your project should
be based on existing source code. Evaluate an appropriate source control
structure based on your code and branching needs. For more information,
see “How To: Structure Your Source Control Folders in Visual Studio Team
Foundation Server.”
Step 1 – Choose a Process Template
Start by selecting your process template. Consider the process
you would like to follow for your project and then examine the different
features provided by each of the two templates supplied by TFS (see below).
Features to evaluate include work item definitions (do they provide sufficient
fields for your needs?), document templates, workflows, check in policies, and
reports.
TFS provides following two process templates:
- MSF for Agile Software Development (MSF Agile) –
This is a lightweight process for small and informal software projects. It
is based on scenarios and context-driven actions and is both project-centric
and team member (people)-centric.
- MSF for CMMI® Process Improvement (MSF CMMI) – This
is designed for more mature software projects. It extends MSF Agile by
providing support for auditing, verification, and formal processes. It
relies on process and conformance to process and is organization-centric.
If required you can customize the supplied process templates
to align them more closely with your processes. For more information about
customizing the process templates see “How To: Customize a Process Template in
Visual Studio Team Foundation Server”.
The remainder of this How To article, assumes that you have
selected the MSF Agile process template.
Step 2 – Create a Team Project
After you have selected the template you want to use, you
are ready to create a new team project. To create a new team project:
- Ensure that Visual Studio is connected to a TFS instance.
- In Team Explorer, right click the server node and then
click New Team Project…
- On the first page of the New Project Creation Wizard,
enter the name of your team project and then click Next.
- On the Select a Process Template page, from the
drop-down list, select the process template you chose in Step 1. For this
example, choose the MSF for Agile Software Development –v4.0 process
template and then click Next.
- On the Specify the Settings for the Project Portal
page, enter the name and description for the team project portal and then
click Next. The name you supply here is used to build the Microsoft
Windows SharePoint® Services Web site for your project portal.
- On the Specify Source Control Settings page, select
Create an empty source control folder and then click Next.
- On the Confirm Team Project Settings page, review
the settings and then click Finish.
This creates a team project on the TFS server based on the
MSF Agile process template.
Step 3 – Create Security Groups (Optional)
When you create a project in TFS, four default groups are
created for that project regardless of your choice of process template. By
default, each of these groups has a predefined set of permissions that govern
what members of those groups are authorized to do. The four groups are:
- Project Administrator
- Contributor
- Reader
- Build Services.
You can create security groups for your team project to
better meet your organization’s security requirements. Creating a security
group is an efficient way to grant a specific set of permissions to a group of
users on your team project. Make sure that you allow only the minimum
permissions necessary for the group, and add only those users or groups who
must belong to this new team project group.
To perform this procedure, you must be a member of the Project
Administrators group although you do not need to be a Microsoft Windows®
administrator.
- In Team Explorer, select the team project for which you
want to create a group.
- On the Team menu, point to Team Project Settings,
and then click Group Membership.
- In the Project Groups dialog box, click New.
- In the Create New Team Foundation Server Group dialog
box, in the Group name box, type the name for the team project
group.
- In the Description box, type a description for the
group.
- Click OK and then Close.
After you have created a team project group, give the group
the appropriate permissions, and add members to the group. By default, a team
project group is created without any permission granted.
Step 4 – Add Team Members in Team Foundation Server
In this step, you identify the resources that will be
working on the project and their roles, and then assign these team members to TFS.
You can add users to existing team project groups or server-level groups. You
must also add members to groups that you create. To perform this procedure, you
must be a member of the Team Foundation Administrators group.
- In Team Explorer, select your team project.
- On the Team menu, point to Team Project Settings,
and then click Group Membership
-Or-
To add users to a server-level group, point to Team Foundation Server
Settings, and then click Group Membership.
- In the Project Groups dialog box, select the group
to which you want to add users, and then click Properties.
- In the Team Foundation Server Group Properties
dialog box, on the Members tab, under Add member, select Windows
User or Group.
- Click Add.
- In the Select Users or Groups dialog box, under Enter
the object names to select, enter the domain name and alias of the
users you want to add in the following format:
domain\username
To add more than one user at a time, separate the entries with a semicolon
(;).
- Click OK twice and then click Close.
Step 5 – Determine Your Iteration Cycle
Iterations are fixed-length chunks of periods in
which you plan, schedule, and perform work. All components of the software
development lifecycle - from requirements definition through analysis, design,
development, coding, and testing - are grouped into these iterations, which
typically last anywhere from 2 to 6 weeks.
In this step you determine the iteration cycle for your
project. The important points to keep in mind while determining the iteration
cycle are:
- The iteration cycle should be long enough to get
substantial work done, and should cover at least a few scenarios
- The iteration cycle should be short enough to be flexible
to accommodate changes and changing priorities.
The length of your iteration cycle will depend upon the size
and complexity of your project. In practice, two-week iteration cycle works for
most projects.
Step 6 – Capture Your Project Scenarios in TFS
In this step, you capture your project scenarios in TFS so
that you can plan better execution of your project and track its progress.
- Create a project back log (PBL) document from inputs provided
by various stake holders, including customers, business analysts, end
users and product managers. The PBL is generally a Microsoft Office Word
document designed mainly to capture requirements.
- Use the PBL as input and scope out various scenarios for your
project.
- You can create all the scenarios at the start of the first
iteration or you can create scenarios as you move through iterations. To
gain a complete picture of your project and to help track progress, you
are recommended that you capture all your scenarios upfront.
To create a scenario in a project that uses the MSF Agile
process template.
- In Team Explorer, expand the project node and then right-click
on the Work Items folder.
- Point to Add Work Item and then click Scenario.
- On the New Scenario page, enter the details for the
Scenario.
- Save your new scenario.
- Repeat the preceding steps for all scenarios that you have
identified for the project.
Step 7 – Identify the Scenarios for the Iteration
In this step, you identify the scenarios to be worked on during
a specific iteration. You repeat this step for each iteration cycle.
- Identify the scenarios to be worked on during a specific
iteration, based on inputs from the project stakeholders and your feature
priorities.
- Assign these scenarios to the iteration
To retrieve work items and assign them to a specific
iteration:
- Expand the Work Items folder, expand the Team Queries
folder, and then double-click the All Scenarios query to display
all the scenarios in your project.
- Double-click the scenario you want to work on in the current
iteration.
- Change the Iteration to the current iteration path
and then click the save icon.
- Repeat the preceding steps for all identified scenarios.
Step 8 – Define Your Quality of Service Requirements
In this step, you define your Quality of Service (QoS) requirements
for each of the scenarios to be worked on during the iteration cycle. You
repeat this step for each iteration cycle. This helps define the acceptance
criteria for the scenario. The inputs for the QoS requirements come from
project goals and requirements and specification documentation, if available.
- Right-click on the Work Items folder of your
project, and point to Add Work Item, and then click Quality of
Service Requirements.
- In the New Quality of Service Requirements page,
add the following details
- Set the Type to an appropriate value such as Performance,
Scalability, Stress or Security.
- Set the Iteration to the current iteration cycle.
- From the Links tab, link the QoS to a specific scenario,
for easier traceability.
- Save the new QoS requirement.
- Create one QoS requirements for each discipline or type of
quality requirements, bearing in mind that each scenario can have multiple
QoS requirements.
- Make sure you create QoS requirements for all of the scenarios
in a specific iteration cycle.
Important – You can break down the QoS requirements into
test tasks later.
Step 9 – Plan Your Iteration
In this step you plan for the iteration by breaking down the
scenarios, QoS requirements, and other work items into tasks, estimating effort
for each task and assigning the tasks to the relevant team members. You repeat this
step for each iteration cycle.
Developer Tasks
- Break down the chosen scenarios into developer stories
- Subdivide the developer stories into developer tasks.
- Capture developer tasks in TFS as task work items.
- In Team Explorer, under your project node, right-click
the Work Items folder, point to Add Work Item and then
click Task.
- In the New Task page, add the following details
- Set Discipline to Development.
- Set Iteration to the current iteration cycle.
- On the Links tab link the task to the specific scenario for easier traceability.
- On the New Task Page, along with the description you can capture the acceptance criteria for the task, which can determine if the task is completed successfully.
- Set the Assigned to field to the developer who will be working on the task.
- Save the new task.
- Repeat the above steps for all the identified tasks.
- Repeat the above steps for all the identified scenarios
for the iteration.
Test Tasks
- Break down the QoS requirements for the identified
scenario into test cases.
- Divide the test cases into test tasks, these test tasks
are captured in TFS as task work items.
- In Team Explorer, under your project node, right-click the
Work Items folder, point to Add Work Item and then click Task.
- In the New Task page, add the following details
- Set Discipline to Test.
- Set Iteration to the current iteration cycle.
- On the Links tab link the task to the specific QoS requirements for easier traceability.
- On the New Task page, along with the description you can capture the acceptance criteria for the task, which can determine if the task is completed successfully.
- Set the Assigned to field to the tester who will be working on the task.
- Save the new task.
- Repeat the above steps for all the identified tasks.
- Repeat the above steps for all the QoS requirements for
the iteration
Others
- Capture any relevant tasks for the iteration for other
disciplines – such as Architecture, Release Management, Project Management
and Requirements - which needs to be tracked.
- Link each of these tasks to the appropriate scenario for
easier traceability.
For large projects that contain a huge number of work items,
you can use the Microsoft Office Excel® integration feature to create work
items in an Excel spread sheet and then upload it to TFS. For more information
see “Working with Work Item Lists in Microsoft Excel” at http://msdn2.microsoft.com/en-us/library/ms181694(VS.80).aspx
For large projects that contain a large number of resources,
you can use the integration feature in Microsoft Office Project to track the
work items and balance task assignment. For more information see “Working with
Work Items in Microsoft Project” at http://msdn2.microsoft.com/en-us/library/ms244368(VS.80).aspx
Step 10 – Monitor Progress
Each process template includes a set of reports that you can
use to track project status and health. Below are the default reports that you
can use to monitor progress:
Bugs
The bug related reports enable you to see the kind of bugs
being generated and fixed and to spot trends. The following bug related reports
are available:
- Bugs by Priority. Are the correct bugs being found?
This report shows you the rate of high priority bugs found vs. low
priority. This report is both of the supplied process templates.
- Bug Rates. How effectively are bugs being found,
fixed and closed? This report shows trends over time for new bugs, bug
backlogs, and bug resolution. This report is available in both of the
supplied process templates.
Release Management
Release management reports enable you to judge how close your
software is to being fit for release. The following release management reports
are available:
- Actual Quality versus Planned Velocity. How many
scenarios can be completed before quality is unacceptable? This report
presents the relationship, for each iteration, of estimated size to
overall quality. This report is available in both process templates.
- Builds. What is the quality of a build? This report
provides a list of available builds including build quality and other
detailed information. This report is available in MSF for CMMI Process
Improvement.
- Quality Indicators. What is the quality of the
software? This report collects test results, bugs code coverage and code
churn into a single report to track project health. This report is
available in MSF Agile and MSF CMMI.
- Velocity. How quickly is the team completing work?
This report shows how quickly the team is completing planned work and show
rates of change from day to day. This report is available in MSF Agile and
MSF CMMI.
- Scenario Details. What scenarios are we building
the application against? This report provides information on each scenario
including completion status, risks and testing progress.
Testing
Testing reports enable you to monitor the effectiveness and
progress of your testing. The following test reports are available:
- Regressions. What tests passed at one point but are
now failing? This report shows a list of all the tests that passed
previously and now are failing. This report is available in MSF CMMI.
- Requirements Test History. How well tested are my
scenarios and requirements? This report shows the progress of testing
against defined scenarios and requirements. This report is available in
MSF CMMI.
- Test Failure Without Active Bug. Are there bugs to
track every known defect? This report shows any tests that have failed and
are not associated with an open bug. This report is available in MSF CMMI.
- Test Passing With Open Bug. Is the bug list up to
date and consistent with application quality? This report shows stale bugs
for which tests are now passing. This report is available in MSF CMMI.
- Load Test Summary. What are the results of load
testing on application performance? This report shows test results for
load testing on your application. This report is available in MSF Agile.
Work Items
Work item reports enable you to assess the current state of
your project and current project progress. The following work item reports are
available.
- Open Issues and Blocked Work Items Trend. How many
open issues remain? This report shows the remaining open issues as well as
the trend toward resolving them. This report is available in MSF CMMI.
- Reactivations. How many work items are being
reactivated? This report shows work items that have been resolved or
closed prematurely. This report is available in MSF Agile and MSF CMMI.
- Related Work Items. What work items are dependent
on other work items? This report shows a list of work items that are
linked to other work items so you trace dependencies. This report is
available in MSF CMMI.
- Remaining Work. How much work is left to be done
and when will it be completed? This report shows work remaining, resolved
and closed over time. Projecting remaining work trends forward can enable
you to predict the point at which you will be code complete. This report
is available in MSF Agile and MSF CMMI.
- Triage. What work items need to be triaged? This
report shows every work item that is still in the proposed state. This
report is available in MSF CMMI.
- Unplanned Work. How much unplanned work is there?
This report charts total work versus remaining work and distinguishes
planned from unplanned. This report is available in MSF Agile and MSF
CMMI.
- Work Items. What are the active work items? This
report lists every active work item. This report is available in MSF CMMI.
- Work Items by Owner. How much work is assigned to
each member of the team? This report shows work items per team member.
This report is available in MSF CMMI.
- Work Items by State. How many active, resolved and
closed work items are there? This report lists work items organized by
state. This report is available in MSF CMMI.
Area and Iteration Consideration
Keep in mind the following key considerations related to
areas and iterations
- Areas are used to organize work in your team project; for
example, you could organize your project work into areas such as a UI
area, an Application area, and a Database area. You can assign scenarios
and work items to the specific areas. Areas are used to group work items
for queries and reports. You can start with a single root-level area and
later as your project matures you can create areas once you need them.
- Iterations are used to define how many times the team will
repeat a particular set of major activities (such as planning, development
and testing) during the course of application development. Iterations are
used to group work items and therefore impact work item creation, work
item queries, and reporting.