Areas and Iterations
Check-in Policies
Process Templates
Security Groups and Permissions
Team Projects
Work Items
Areas and Iterations
- Use areas for better traceability.
- Use iterations to represent milestones in your project.
- Determine appropriate iteration cycle duration.
Use Areas for Better Traceability
Use areas in your team project to keep project tasks, bugs,
requirements, and other work items organized. You can also set permissions on
areas to restrict access to various parts of your team project.
Use areas to represent logical or physical components, and then
create sub-areas to represent specific features. This structure helps you keep
your work items organized and can be used to improve traceability by component
or feature.
To create areas for your project
- In Team Explorer, click your team
project.
- On the Team menu, point to Team Project Settings,
and then click Areas and Iterations.
- In the Areas and Iterations dialog box, click the Area
tab.
- Click the Add a child node toolbar button.
- Right-click the new node, click Rename, and then
type the area name you want.
- Click the Area node.
- Repeat steps 2, 3, and 4 to create additional areas and to
create a hierarchy for your project structure.
Beware of creating too complex area structure, while areas
allow you to partition work items permissions, there is overhead associated
with managing those permissions for complex trees. It may also be problematic
to copy over the structure/ permissions to other Team projects.
Additional Resources
Use Iterations to Represent Milestones in Your
Project
Use iterations to define how many times your team will repeat
a particular set of major activities (such as planning, implementation, or testing)
during the course of application development. This set of major activities
should represent a milestone for the project with a quantifiable outcome such
as feature complete or component complete.
To create an iteration
- In Team Explorer, click your team project.
- On the Team menu, point to Team Project Settings,
and then click Areas and Iterations.
- In the Areas and Iterations dialog box, click the Iteration
tab.
- Click the Add a child node toolbar button.
- Right-click the new node, click Rename, and then
type the iteration name.
- Click the Iteration node.
- Repeat steps 2, 3, and 4 to create additional iterations
identified for your project.
- Click Close.
Note: The Microsoft® Solutions Framework (MSF) for
Agile Software Development (MSF Agile) process template includes three
predefined iterations. Depending on your specific requirements, you can delete
these iterations, rename them instead of creating new ones, or leave them
unchanged.
Additional Resources
Determine Appropriate Iteration
Cycle Duration
When setting up your team project, determine the appropriate
iteration cycle duration based on the size and complexity of your project.
Keep the following key points in mind when determining
iteration cycle duration:
- The iteration cycle should be long enough to allow team
members to get substantial work done, and should cover at least a few different
scenarios.
- The iteration cycle should be short enough to flexibly
accommodate changes and priorities.
In practice, a two-week iteration cycle works for most
projects.
Additional Resources
Check-in Policies
- Use check-in policies to enforce code quality.
- Use check-in policies to ensure that developers
associate work items with check-ins.
- Create check-in policies to enforce coding standards.
- Set up notifications to inform you when developers
bypass check-in policies.
Use Check-in Policies to Enforce Code Quality
Use a combination of code analysis and testing policies to
improve check-in quality for your project. For example, use the supplied
testing policy to ensure that specific tests are executed and passed prior to
allowing source to be checked into Microsoft Visual Studio® 2005 Team
Foundation Server (TFS) source control. You can also configure a code analysis
policy to help ensure that your code meets certain quality standards by
ensuring that security, performance, portability, maintainability, and
reliability rules are passed.
By enforcing this type of check-in policy in addition to
policies that enforce coding standards and guidelines, you ensure that your
code meets a specific quality standard.
To enforce a code analysis check-in policy for a team
project
- In Team Explorer, right-click your team project, point to Team
Project Settings, and then click Source Control.
- Click the Check-in Policy tab, click Add,
and then select and configure the appropriate policy.
Additional Resources
Use Check-in Policies to Ensure That
Developers Associate Work Items with Check-ins
Set the Work Items check-in policy to force developers to
associate their check-in with a work item.
If a build breaks, it is important that you know what
changesets are associated with the build, and what work items those changesets
are associated with, so that you can identify the developer responsible for
checking in this code and the area of the project on which the developer is working.
To set the Work Items check-in policy to force developers
to associate their check-in with a work item
- In Team Explorer, right-click your team project, select
Team Project Settings, and then click Source Control.
- Click the Check-in Policy tab.
- Click Add and then select and configure the Work
Item check-in policy.
Additional Resources
Create Check-in Policies to Enforce
Coding Standards
The project you are working on may require coding standards
that are not covered by static code analysis or by existing check-in policies.
For example, your project may require that your code never uses the tab
character, or that all check-ins require comments. You can create new check-in
policies to cover these scenarios.
To enforce a code analysis check-in policy for a team
project
- In Team Explorer, right-click your team project, point to Team
Project Settings, and then click Source Control.
- Click the Check-in Policy tab and then click Add.
- In the Add Check-in Policy dialog box, select Code
Analysis and then click OK.
- In the Code Analysis Policy Editor, select either Enforce
C/C++ Code Analysis (/analyze) or Enforce Code Analysis For
Managed Code. Select both if your project contains a combination of
managed and unmanaged code.
- If you select managed code analysis, configure your
required rule settings for managed code analysis based on your required
coding standards.
- This determines precisely which rules are enforced.
You can also create a custom check-in policy to perform
checks that are not available by default. For example, you can disallow code
patterns such as banned application programming interface (API) calls, or you
can write a policy to enforce your team’s specific coding style guidelines,
such as where braces should be positioned within your source code.
Additional Resources
Set Up Notifications to Inform You When
Developers Bypass Check-in Policies
Team Foundation Server Version Control does not prevent you from
overriding a check-in policy. However, you can use the following steps to
detect if a check-in policy has been overridden:
- Use the Team Foundation Server Eventing Service (from the
Team Foundation Core Services API) for hooking check-in events.
- Write a Notify method that parses the details of
the changeset and then reacts to it if an override has occurred.
Alternatively, you can manually scan changeset history to
discover policy overrides.
Additional Resources
Process Templates
- Use the MSF Agile process template when working on
projects that only require a lightweight or informal process.
- Use the MSF CMMI process template when working on
projects requiring a more formal process or conformance with CMMI
standards.
- Consider using a minimal process template.
- Modify an existing process template to match your team’s
process.
Use the MSF Agile Process Template When Working on
Projects That Only Require a Lightweight or Informal Process
When using Test-Driven Development (TDD) or other agile
methodologies, you should use the MSF for Agile Software Development (MSF
Agile) process template. This is a lightweight process for agile software
projects. You should use this project template as your first choice, unless you
specifically need the additional process improvement features provided by the
MSF for CMMI Software Development (MSF CMMI) process template.
You can easily edit the MSF Agile process template and modify
it to suit your process requirements.
Additional Resources
Use the MSF CMMI Process Template When Working
on Projects Requiring a More Formal Process or Conformance with CMMI Standards
When using a formal software development process aimed at
improving the existing process, you should use the MSF for CMMI Software
Development (MS CMMI) process template.
You can easily edit and modify this process template to suit
your process requirements.
Additional Resources
Consider Using a Minimal Process Template
Many teams do not require support for all parts of a
standard team project. For example, many teams want to use the source control
portion of a team project but not the Microsoft Office SharePoint® portal. Team
project templates can be modified, and it is possible to remove some parts of
the template that you do not need. When you modify the template, you will need
to keep the Group Permissions and Classifications sections; however, you can
keep or remove the other sections as you see fit.
In order to create a minimal process template, you use the
Process Template Manager to download the template to your local computer, edit
the template to remove the sections you are not going to use, and then upload
the template back to the server.
Additional Resources
Modify an Existing Process Template to Match
Your Team’s Process
The project you are working on might not fit the out-of-box
process templates provided with Microsoft Visual Studio Team System (VSTS). You
might need a different work item type, or you might be using an entirely
different process methodology. In this case, you should modify the existing
process template. Choose the process template that most closely meets your
process requirements and then modify the template as necessary.
The following areas of the process templates commonly need
to be customized:
- Groups and Permissions
- Work Item Types
- Source Control Check-in Notes and Policies
- Areas and Iterations
- Reports
- Team Portal
- Process Guidance
Additional Resources
Security Groups and Permissions
- Create security groups to grant a specific set of
permissions.
- Assign team members to the appropriate security group.
Create Security Groups to Grant a Specific
Set of Permissions
When you create a project in Team Foundation Server, four
default groups are created for that project regardless of your choice of
process template. By default, each of these groups has a set of permissions
defined for it that governs what members of those groups are authorized to do.
The four groups are:
- Project Administrator
- Contributor
- Reader
- Build Services.
You can create security groups for your team project to
better meet your organization’s security requirements. Creating a security
group is an efficient way to grant a specific set of permissions to a group of
users on your team project. Make sure that you allow only the minimum
permissions necessary for the group, and add only those users or groups who
must belong to this new team project group.
Additionally use the following guidelines:
- Do not change the permissions on default groups (or if you
do, do it in every project the same way)
- Use Active Directory (AD) groups for membership on server
level only
- Use TFS groups for permissions settings (rather than AD
groups)
- Never deny anything (usually deny means that the
partitioning you use is less than ideal); make sure you reason is sound
when you do
Additional Resources
Assign Team Members to the Appropriate Security
Group
Identify the team members who will be working on the project
and their roles, and assign these team members to TFS by using existing team
project groups, server-level groups, or custom security groups that you create.
When assigning members to a security group, assign only
those members who need the permissions available to that security group. If
necessary, you can create custom security groups with appropriate security
permissions and then assign users to those security groups.
Additional Resources
Team Projects
- Create one team project per application if you want to
migrate work items and other assets between application versions.
- Create one team project per version if you want to
start with new work items and other assets with each application version.
- Create one team project per team when working with
large projects that span multiple projects.
- Grant only required permissions on project assets.
- Structure your source tree to support branching.
Create One Team Project per Application if You
Want to Migrate Work Items and Other Assets Between Application Versions
If you want to carry forward not only source code but also work
items and other TFS assets between releases, consider using one team project
per application. When you use a single team project for multiple versions of
the application, all of the TFS assets are carried forward automatically for
the next release. When you are ready to release a new version of your
application, you can create a branch within the project to represent the
release and isolate that code.
Keep the following key points in mind when using one project
per application:
- Parallel releases are forced to share work items schema,
check in policies, and process guidance.
- Reporting is more difficult; because reports default to
the entire project, you must add filtering by release.
- If you have hundreds of applications, each in its own
project, you will run up against TFS performance and scale limits.
- You will accumulate ‘baggage’ over multiple releases. The
easiest way to address this issue is to create a new project and branch the
code you want to carry forward into that project.
Additional Resources
Create One Team Project per Version if You
Want to Start with New Work Items and Other Assets with Each Application Version
If you want each release to start fresh without carrying
forward work items and other TFS assets, consider using one project per
release. When you use a new project for each release, you can modify work item
schema, workflow, check-in policies, and other assets without impacting the old
release. This can be especially useful if the old release will be maintained by
a separate team such as a sustained engineering team who may have a different
process and workflow than your main development team.
Keep the following key points in mind when using one project
per release:
- Although it is very easy to move the source code from one
project to another, it is difficult to move work items and other TFS
assets from one project to another. Because work items can only be copied
one at a time to another project, if you want to copy sets of work items,
you will need to write your own utility.
- If you have hundreds of applications and releases, each in
its own project, you will run up against TFS performance and scale limits.
- Choose a structure you can live with in the long term
because restructuring existing team projects is difficult.
- Source can be easily shared among team projects as follows:
- Branch source from one project to another.
- Map source from another project into your workspace.
- Team Foundation Server can scale to ~500 projects by using
the MSF Agile process template or 250 projects using the MSF CMMI process
template. If you create your own process template or customize an existing
process template, keep in mind that the work item schema has the largest
impact on server scalability. A complex schema will result in a server
capable of supporting fewer projects.
- You will have to carry over all the areas from the
original project; and perhaps also change the permissions in source
control.
Additional Resources
Grant Only Required Permissions on Project
Assets
When creating team projects, review the default security
groups created by the process and, if necessary, create security groups with
appropriate permissions. You then assign the project members to appropriate
groups to ensure that each member gets only the permissions he or she requires on
project assets.
Additional Resources
Structure Your Source Tree to Support Branching
When creating your source tree structure, make sure that it
supports branching. Keep separate folders for source and for other project
assets, so that if isolation development is required in the future, you can
simply branch the source folder. Also make sure that you maintain separate
folders for each component within the source folder, so that partial branching
can be performed if required.
Segregate other entities such as shared code, unit tests,
library dependencies, and so on by using folders so that they can be excluded or
included during branching as required.
The following is an example of a source tree structure that supports
branching:
- Main – Container for all assets you need to ship
the product
- Source – Container for everything you need in
order to build
- Code – Container for source code
- Shared Code – Container for source code that is
shared from other projects
- Unit Tests – Container for unit tests
- Lib – Container for binary dependencies
- Docs – Container for documentation that will ship
with the product
- Installer – Container for installer source code
and binaries
- Builds – Container for Team Build scripts
- Tests – Container for test team test cases
Additional Resources
Work Items
- Capture your scenarios at the start of your project.
- Define your Quality of Service requirements
appropriately.
- Break scenarios into manageable, modular development
tasks.
- Set acceptance criteria for each task.
- Link requirements and tasks to scenarios.
- Use Microsoft Excel for bulk editing of work items.
Capture Your Scenarios at the Start
of Your Project
Create and capture a set of project scenarios at the start of
your project. This helps you to gain a complete picture of your project and can
later be used track progress. During the course of development, you can modify existing
scenarios or add new scenarios to represent what you learn over time.
To capture scenarios at the start of the project
- Use the project back log (PBL) document, which is a
requirement document based on input from various stakeholders (including
customers, business analysts, end users, and product managers), and scope
out the scenarios for your project.
- In Team Explorer, expand the project node, right-click the
Work Items folder, point to Add Work Item, and then click Scenario.
- On the New Scenario page, enter the details for the scenario.
Make sure to set the Iteration to Iteration 999.
- Save your new scenario.
- Repeat the above steps for all scenarios that you have
identified for the project.
Additional Resources
Define Your Quality of Service Requirements
Appropriately
Define your Quality of Service (QoS) requirements for each
of the scenarios to be worked on during the iteration cycle. This helps to define
the acceptance criteria for the scenario. The inputs for the QoS requirements come
from project goals and requirements and specification documentation, if
available.
To define your QoS requirements
- Right-click your project’s Work Items folder, point to Add
Work Item, and then click Quality of Service Requirements.
- On the New Quality of Service Requirements page, add the
following details:
- Set the Type to an appropriate value such as
performance, scalability, stress, or security.
- Set the Iteration to the current iteration cycle.
- From the Links tab, link the QoS to a specific
scenario for easier traceability.
- Save the new QoS requirement.
- Create one QoS requirement for each discipline or type of
quality requirement, bearing in mind that each scenario can have multiple
QoS requirements.
- Make sure that you create QoS requirements for all of the
scenarios being worked on during a specific iteration cycle.
Important: You can break down the QoS requirements into
test tasks later.
Additional Resources
Break Scenarios into Manageable, Modular
Development Tasks
During iteration planning, break your scenarios into user
stories and then further break the user stories into development tasks. Make
sure that the development tasks you create are manageable and modular. The tasks
should not last for more than one or two days. If they are larger than this, you
need to break the tasks down into smaller tasks or sub-tasks. Doing this contributes
to schedule flexibility and improved manageability of the project.
To break scenarios into manageable, modular development
tasks
- Break down the chosen scenarios into developer stories.
- Subdivide the developer stories into developer tasks.
- Capture developer tasks in TFS as task work items as
follows:
- In Team Explorer, under your project node, right-click the Work Items folder, point to Add Work Item, and then click Task.
- On the New Task page, add the following details:
- Set the Discipline to Development.
- Set the Iteration to the current iteration cycle.
- On the Links tab, link the task to the specific scenario for easier traceability.
- On this tab, along with the description, you can capture the acceptance criteria for the task, which can determine if the task has been successfully completed.
- Set the Assigned to field to the developer who will work on the task.
- Save the new task.
- Repeat the above steps for all the identified tasks.
- Repeat the above steps for all the identified scenarios
for the iteration.
Additional Resources
Set Acceptance Criteria for Each Task
Development tasks, when defined, should include acceptance
criteria that allow a developer to decide when the task is complete. Depending
on the process template you are using, this could be done in two different
ways:
- MSF Agile – If you are using MSF Agile without a
formal work item type requirement, it is best to include acceptance
criteria as text in the work item itself. Start with a bulleted list and
add more detail as necessary.
- MSF CMMI – If you are using MSF CMMI, you can use
formal requirements to define acceptance criteria for a task. The first
step is to define your requirements. You then create the development task
that will be used to implement these requirements and link the task to the
requirements so that the developer can check against them, and so that
there is traceability from requirements to task.
The acceptance criteria are most often defined as a user
experience requirement in the form of a mini-scenario or a QoS requirement. After
the acceptance criteria have been met, the developer can mark the task as
complete and move to the next task.
Additional Resources
Link Requirements and Tasks to Scenarios
When creating new work items such as tasks, bugs, issues, or
QoS requirements, make sure that you link these work items to the scenarios
that drove their creation. This helps ensure that each work item is driven by a
real user scenario and can be used to better track scenario completion progress
during the course of your development iterations.
To links new tasks, bugs, issues, or QoS work items to
scenarios
- In the New work item page, click the Links
tab, on the Links tab click the Add button.
- In the Add Link dialog box, under Link Type,
select Scenario.
- Click Browse to find the scenarios in your team
project.
- In the list, select the scenario to which you want to link
and then click OK.
- In the Comment box, type a comment that explains
how the work item is related. The Description box is filled in
automatically.
- Click OK.
Additional Resources
Use Microsoft Excel for Bulk Editing of
Work Items
Team Foundation Server does not support bulk editing of work
items. Instead, you must edit each work item individually. If you need to
modify a large number of work items in a short period of time—for example,
during a triage meeting—consider using Microsoft Office Excel® to ease the
task. Work items can be exported from TFS to Excel, modified, and then imported
back into TFS to retain any edits that you made.
To create a work item list in Excel and edit it
- In Microsoft Office Excel, on the Team menu, click New
List.
- Under Connect to a Team Foundation Server, select
the server to connect to, or click Servers to enter the server
information.
- Under Team Projects, select the team project on the
Team Foundation Server with which you want to work.
- The document will be bound to this team project.
- Click OK.
- Select the type of list you want. To create a query list,
select the Query List option and then select a team query from the Select
a Query drop-down list.
- Select the columns you want to appear in the new work item
list.
- Import the desired work items. For more information, see
How to: Import Work Items in Microsoft Excel or Microsoft Project at http://msdn2.microsoft.com/en-us/library/ms181676(VS.80).aspx
- You can now edit the work items and then publish the
updated work items to the work item database by clicking Publish
Changes on the Team menu.
Additional Resources
Team Foundation Project Management Resources
.gif)