This section contains information about the elements defined by the ChangeList Schema.

The following shows the XML element structure used for changeXML strings in Statusing methods for Microsoft Project Server 2010.

<Changes>

  <Proj>

    <Assn>

      <Change>…</Change>

      <PeriodChange>…</PeriodChange>

      <SimpleCustomFieldChange>…</SimpleCustomFieldChange>

      <LookupTableCustomFieldChange>

        <LookupTableValue>…</LookupTableValue>

      </LookupTableCustomFieldChange>

    </Assn>

    <Task>

      <Change>…</Change>

    </Task>

  </Proj>

</Changes>

For example, the UpdateStatus_ManualTasks code sample in the UpdateStatus method creates the following changeXml string (without the newline characters). The PID attribute is the value of the s_apid_pct_wrk_complete field.

<Changes>
  <Proj ID="4919eb1d-e0c1-4bc4-8e5e-c1717b1ba276">
    <Assn ID="4cc3f5fc-04dd-4947-9ed4-351f2ec70587" ResID="ce06af7d-185b-49ba-bb89-56d2a35d4bf6">
      <Change PID="251658274">75</Change>
    </Assn>
  </Proj>
</Changes>