Occurs before the user changes the value of a task field. Uses the
EventInfo object parameter.
Syntax
expression.ProjectBeforeTaskChange2(tsk, Field, NewVal, Info)
expression A variable that represents an Application object.
Parameters
| Name | Required/Optional | Data Type | Description |
|---|
| tsk | Required | Task | The task whose field is being changed. |
| Field | Required | PjField | The field being changed. If more than one field is changed by the user, the event is fired for each field changed. Can be one of the following PjField constants:
| pjTaskActualCost | pjTaskHyperlinkSubAddress | | pjTaskActualDuration | pjTaskID | | pjTaskActualFinish | pjTaskIgnoreResourceCalendar | | pjTaskActualOvertimeCost | pjTaskIndex | | pjTaskActualOvertimeWork | pjTaskIndicators | | pjTaskActualOvertimeWorkProtected | pjTaskIsAssignment | | pjTaskActualStart | pjTaskLateFinish | | pjTaskActualWork | pjTaskLateStart | | pjTaskActualWorkProtected | pjTaskLevelAssignments | | pjTaskACWP | pjTaskLevelCanSplit | | pjTaskAssignmentDelay | pjTaskLevelDelay | | pjTaskAssignmentUnits | pjTaskLinkedFields | | pjTaskBaseline1-10Cost | pjTaskMarked | | pjTaskBaseline1-10Duration | pjTaskMilestone | | pjTaskBaseline1-10DurationEstimated | pjTaskName | | pjTaskBaseline1-10Finish | pjTaskNotes | | pjTaskBaseline1-10Start | pjTaskNumber1-20 | | pjTaskBaseline1-10Work | pjTaskObjects | | pjTaskBaselineCost | pjTaskOutlineCode1-10 | | pjTaskBaselineDuration | pjTaskOutlineLevel | | pjTaskBaselineDurationEstimated | pjTaskOutlineNumber | | pjTaskBaselineFinish | pjTaskOverallocated | | pjTaskBaselineStart | pjTaskOvertimeCost | | pjTaskBaselineWork | pjTaskOvertimeWork | | pjTaskBCWP | pjTaskParentTask | | pjTaskBCWS | pjTaskPercentComplete | | pjTaskCalendar | pjTaskPercentWorkComplete | | pjTaskConfirmed | pjTaskPhysicalPercentComplete | | pjTaskConstraintDate | pjTaskPredecessors | | pjTaskConstraintType | pjTaskPreleveledFinish | | pjTaskContact | pjTaskPreleveledStart | | pjTaskCost | pjTaskPriority | | pjTaskCost1-10 | pjTaskProject | | pjTaskCostRateTable | pjTaskRecurring | | pjTaskCostVariance | pjTaskRegularWork | | pjTaskCPI | pjTaskRemainingCost | | pjTaskCreated | pjTaskRemainingDuration | | pjTaskCritical | pjTaskRemainingOvertimeCost | | pjTaskCV | pjTaskRemainingOvertimeWork | | pjTaskCVPercent | pjTaskRemainingWork | | pjTaskDate1-10 | pjTaskResourceEnterpriseMultiValueCode20-29 | | pjTaskDeadline | pjTaskResourceEnterpriseOutlineCode1-29 | | pjTaskDelay | pjTaskResourceEnterpriseRBS | | pjTaskDemandedRequest | pjTaskResourceGroup | | pjTaskDuration | pjTaskResourceInitials | | pjTaskDuration1-10 | pjTaskResourceNames | | pjTaskDuration1-10Estimated | pjTaskResourcePhonetics | | pjTaskDurationVariance | pjTaskResourceType | | pjTaskEAC | pjTaskResponsePending | | pjTaskEarlyFinish | pjTaskResume | | pjTaskEarlyStart | pjTaskResumeNoEarlierThan | | pjTaskEarnedValueMethod | pjTaskRollup | | pjTaskEffortDriven | pjTaskSheetNotes | | pjTaskEnterpriseCost1-10 | pjTaskSPI | | pjTaskEnterpriseDate1-30 | pjTaskStart | | pjTaskEnterpriseDuration1-10 | pjTaskStart1-10 | | pjTaskEnterpriseFlag1-20 | pjTaskStartSlack | | pjTaskEnterpriseNumber1-40 | pjTaskStartVariance | | pjTaskEnterpriseOutlineCode1-30 | pjTaskStatus | | pjTaskEnterpriseProjectCost1-10 | pjTaskStatusIndicator | | pjTaskEnterpriseProjectDate1-30 | pjTaskStop | | pjTaskEnterpriseProjectDuration1-10 | pjTaskSubproject | | pjTaskEnterpriseProjectFlag1-20 | pjTaskSubprojectReadOnly | | pjTaskEnterpriseProjectNumber1-40 | pjTaskSuccessors | | pjTaskEnterpriseProjectOutlineCode1-30 | pjTaskSummary | | pjTaskEnterpriseProjectText1-40 | pjTaskSV | | pjTaskEnterpriseText1-40 | pjTaskSVPercent | | pjTaskEstimated | pjTaskTCPI | | pjTaskExternalTask | pjTaskTeamStatusPending | | pjTaskFinish | pjTaskText1-30 | | pjTaskFinish1-10 | pjTaskTotalSlack | | pjTaskFinishSlack | pjTaskType | | pjTaskFinishVariance | pjTaskUniqueID | | pjTaskFixedCost | pjTaskUniquePredecessors | | pjTaskFixedCostAccrual | pjTaskUniqueSuccessors | | pjTaskFixedDuration | pjTaskUpdateNeeded | | pjTaskFlag1-20 | pjTaskVAC | | pjTaskFreeSlack | pjTaskWBS | | pjTaskGroupBySummary | pjTaskWBSPredecessors | | pjTaskHideBar | pjTaskWBSSuccessors | | pjTaskHyperlink | pjTaskWork | | pjTaskHyperlinkAddress | pjTaskWorkContour | | pjTaskHyperlinkHref | pjTaskWorkVariance | | pjTaskHyperlinkScreenTip | |
|
| NewVal | Required | Variant | The new value for the field specified with Field. |
| Info | Required | EventInfo | EventInfo.Cancel is False when the event occurs. If the event procedure sets this argument to True, the value for the field specified with Field is not changed.
|
Return Value
nothing
Remarks
Project events do not occur when the project is embedded in another document or application.
The ProjectBeforeTaskChange2 event doesn't occur when timescaled data changes, when constraint data in the Task Details Form changes, when a task is split by manipulating its task bar on the Gantt Chart, when changes are made to outline level or outline number, when a baseline is saved, when a baseline is cleared, when an entire task row is pasted, during resource pool operations, when inserting or removing a subproject, or when changes have been made using a custom form.