Copy a BOM from the Bills of materials form

Dynamics AX 4.0
  1. Click > .

  2. On the header of the form, press CTRL+N.

  3. In the field, enter the name of the BOM, select an , and then click to confirm the BOM.

  4. On the lines of the form, press CTRL+N.

  5. In the field, select the item that the BOM should be attached to, and enter the remaining information.

  6. Click to create the BOM lines.

  7. In the form, click > .

  8. In the form, choose between copying from base data or from production.

    • To copy from base data, select the item number that the BOM is attached to, the configuration to be copied from, and the BOM number.

    • To copy from production, enter the production number from which to copy.

  9. In the form, choose between copying to base data or to production.

    • To copy to base data, enter a BOM number to be copied to.

    • To copy to production, enter the production number to be copied to.

  10. In the area, you can mark whether the BOM should replace or add data on the BOM item or the production.